Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Recently, the world's largest rooftop photovoltaic project in a single factory - Zhongshan Galanz Roof Distributed Solar Photovoltaic Power Generation Application Demonstration Project Phase I was successfully connected to the grid for power generation
.
"Zhongshan Galanz Roof Distributed Solar Photovoltaic Power Generation Application Demonstration Project" is invested and built by Nangrid Energy Company, with an installed capacity of 52 MW, arranged on the roof of 42 buildings with a total of 600,000 square meters in Galanz Zhongshan base, which is currently the world's largest single-plant distributed photovoltaic power generation project and the first 10 kV photovoltaic power generation project
put into operation in Zhongshan.
The power generated by the project is "mainly consumed by the factory itself, and a small amount of surplus electricity is sent to the grid"
.
After all 52 MW are put into operation, it is expected that the annual photovoltaic power generation capacity will be 50 million kWh, accounting for nearly 1/3 of the electricity consumption of the plant, which can save a lot of energy costs for enterprises, equivalent to saving 16,900 tons of standard coal and reducing carbon dioxide by 43,000 tons per year, with good economic and social benefits
.
According to the project engineer, Nangrid Energy Company started the construction of the project on August 13, 2014 using the
"contract energy management" mode.
Through the efforts in December, the laying of all 52 MW rooftop photovoltaic modules has been completed
.
During the construction process, in order to ensure the high-quality and efficient completion of the project construction tasks, Nanwang Energy Company used mechanical pipe jacking construction technology to avoid damage to the factory roads; The use of domestic or international first-class equipment to ensure the quality of the project; Strengthen the roof of the factory building, maximize the use of resources, and achieve a win-win
situation.
Recently, the world's largest rooftop photovoltaic project in a single factory - Zhongshan Galanz Roof Distributed Solar Photovoltaic Power Generation Application Demonstration Project Phase I was successfully connected to the grid for power generation
.
"Zhongshan Galanz Roof Distributed Solar Photovoltaic Power Generation Application Demonstration Project" is invested and built by Nangrid Energy Company, with an installed capacity of 52 MW, arranged on the roof of 42 buildings with a total of 600,000 square meters in Galanz Zhongshan base, which is currently the world's largest single-plant distributed photovoltaic power generation project and the first 10 kV photovoltaic power generation project
put into operation in Zhongshan.
The power generated by the project is "mainly consumed by the factory itself, and a small amount of surplus electricity is sent to the grid"
.
After all 52 MW are put into operation, it is expected that the annual photovoltaic power generation capacity will be 50 million kWh, accounting for nearly 1/3 of the electricity consumption of the plant, which can save a lot of energy costs for enterprises, equivalent to saving 16,900 tons of standard coal and reducing carbon dioxide by 43,000 tons per year, with good economic and social benefits
.
According to the project engineer, Nangrid Energy Company started the construction of the project on August 13, 2014 using the
"contract energy management" mode.
Through the efforts in December, the laying of all 52 MW rooftop photovoltaic modules has been completed
.
During the construction process, in order to ensure the high-quality and efficient completion of the project construction tasks, Nanwang Energy Company used mechanical pipe jacking construction technology to avoid damage to the factory roads; The use of domestic or international first-class equipment to ensure the quality of the project; Strengthen the roof of the factory building, maximize the use of resources, and achieve a win-win
situation.