Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Recently, some investors asked Rongsheng Petrochemical on the interactive platform: Under the dual-carbon policy, is the second phase of Zhejiang Petrochemical, a holding subsidiary, put into production as scheduled? Is the company's electricity consumption situation at the end of 2021 more severe than that at the end of 2020? Rongsheng Petrochemical replied that: the company's current production and operation are all normal, and it is basically not affected by electricity restrictions.
In addition, some netizens raised questions: "After the company's 40 million tons/year refining and chemical integration project (Phase I) atmospheric and vacuum and related public works units are put into operation, it will be announced that the whole year will be put into operation in about 7 months; the second phase of atmospheric and vacuum and Relevant public works devices have been put into operation in November 2020, and it has been 12 months since then, and no full-scale production has been announced yet
The construction of the 700,000-ton/year high-pressure polyethylene project has entered the final stage
Since the beginning of November, the Zhejiang Petrochemical Phase II 700,000-ton/year high-pressure polyethylene project undertaken by Shijian Company of Refining and Chemical Engineering has been strengthened by the project department of Shijian Company to strengthen process control and promote the construction of the project at full speed, creating favorable conditions for the plant to be put into operation
It is understood that the 700,000 tons/year high-pressure polyethylene project consists of two major units, 300,000 tons/year LDPE-EVA and 400,000 tons/year LDPE
In order to strengthen on-site safety management and control, the project department continues to promote the concept of full participation, full process control, and comprehensive management to improve the safety quality of all employees
As of November 8, the instrumentation commissioning, thermal insulation, and equipment pipeline purging of the 300,000-ton/year LDPE-EVA plant have been basically completed, and the instrumentation commissioning and insulation of the 400,000-ton/year LDPE plant have been advanced efficiently.