-
Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
The Yunnan Provincial Development and Reform Commission approved four projects: Monkey Mountain Wind Farm in Honghe Prefecture, Tianma Mountain Wind Farm Phase II Project in Wenshan Prefecture, Yongning Wind Farm Project in Honghe Prefecture, and Xianrendongpo Wind Farm Project in Kaiyuan City, Honghe Prefecture, with a total scale of 1,350 MW
.
Monkey Mountain Wind Farm:
The project is located in the old city of
Red River State.
The total installed capacity of the project is 200 MW, and 50 wind turbines are mainly constructed, with a single capacity of 4 MW
.
The construction period of the project is 12 months
.
The total dynamic investment of the project is 1286.
1197 million yuan, and the total static investment is 126151.
46 million yuan, of which the project capital is calculated as 20% of the total investment, which is self-financed by the enterprise, and the rest of the funds are borrowed
from commercial banks.
Tianma Mountain Wind Farm Phase II Project:
The project construction site is located in Yanshan County
, Wenshan Prefecture.
The total installed capacity of the project is 50 MW, and 12 wind turbines are mainly constructed, including 10 wind turbines with a single capacity of 4 MW and 2 wind turbines with a single capacity of 5 MW
.
The construction period of the project is 12 months
.
The total dynamic investment of the project is 315.
9859 million yuan, and the total static investment is 311.
4619 million yuan, of which the project capital is calculated as 30% of the total investment, which is self-financed by the enterprise, and the rest of the funds are borrowed
from commercial banks.
Yongning Wind Farm Project:
The project construction site is located in Luxi County and Maitreya City, Honghe State
.
The total installed capacity of the project is 750 MW, and 157 wind turbines are mainly constructed, including 74 wind turbines with a single capacity of 4.
2 MW, 82 wind turbines with a single capacity of 5.
3 MW, and 1 wind turbine with a single capacity of 4.
6 MW
.
The construction period of the project is 18 months
.
The total dynamic investment of the project is 47070684 million yuan, and the total static investment is 456629.
29 million yuan, of which the project capital is calculated as 20% of the total investment, which is self-financed by the enterprise, and the rest of the funds are borrowed
from commercial banks.
Xianrendongpo Wind Farm Project:
The project construction site is located in Kaiyuan City,
Honghe Prefecture.
The total installed capacity of the project is 350 MW, and 97 wind turbines are mainly constructed, including 59 wind turbines with a single capacity of 4 MW and 38 wind turbines with a single capacity of 3 MW
.
The construction period of the project is 12 months
.
The total dynamic investment of the project is 27196749 million yuan, and the total static investment is 26676441000 yuan, of which the project capital is calculated as 20% of the total investment, which is self-financed by the enterprise, and the rest of the funds are borrowed
from commercial banks.
In addition, the Yunnan Provincial Development and Reform Commission emphasized in its approval reply that if all the above-mentioned projects have not started construction for 2 years from the date of the approval decision or the consent to the change decision, and it is necessary to postpone the start of construction, the project is requested to apply to the Provincial Development and Reform Commission for an extension of construction
30 working days before the expiration of the two-year period.
The start of construction can only be postponed once, and the maximum period shall not exceed 1 year
.
Where the State has other provisions on the postponement of the start of construction of a project, follow those provisions
.
The Yunnan Provincial Development and Reform Commission approved four projects: Monkey Mountain Wind Farm in Honghe Prefecture, Tianma Mountain Wind Farm Phase II Project in Wenshan Prefecture, Yongning Wind Farm Project in Honghe Prefecture, and Xianrendongpo Wind Farm Project in Kaiyuan City, Honghe Prefecture, with a total scale of 1,350 MW
.
Monkey Mountain Wind Farm:
The project is located in the old city of
Red River State.
The total installed capacity of the project is 200 MW, and 50 wind turbines are mainly constructed, with a single capacity of 4 MW
.
The construction period of the project is 12 months
.
The total dynamic investment of the project is 1286.
1197 million yuan, and the total static investment is 126151.
46 million yuan, of which the project capital is calculated as 20% of the total investment, which is self-financed by the enterprise, and the rest of the funds are borrowed
from commercial banks.
Tianma Mountain Wind Farm Phase II Project:
The project construction site is located in Yanshan County
, Wenshan Prefecture.
The total installed capacity of the project is 50 MW, and 12 wind turbines are mainly constructed, including 10 wind turbines with a single capacity of 4 MW and 2 wind turbines with a single capacity of 5 MW
.
The construction period of the project is 12 months
.
The total dynamic investment of the project is 315.
9859 million yuan, and the total static investment is 311.
4619 million yuan, of which the project capital is calculated as 30% of the total investment, which is self-financed by the enterprise, and the rest of the funds are borrowed
from commercial banks.
Yongning Wind Farm Project:
The project construction site is located in Luxi County and Maitreya City, Honghe State
.
The total installed capacity of the project is 750 MW, and 157 wind turbines are mainly constructed, including 74 wind turbines with a single capacity of 4.
2 MW, 82 wind turbines with a single capacity of 5.
3 MW, and 1 wind turbine with a single capacity of 4.
6 MW
.
The construction period of the project is 18 months
.
The total dynamic investment of the project is 47070684 million yuan, and the total static investment is 456629.
29 million yuan, of which the project capital is calculated as 20% of the total investment, which is self-financed by the enterprise, and the rest of the funds are borrowed
from commercial banks.
Xianrendongpo Wind Farm Project:
The project construction site is located in Kaiyuan City,
Honghe Prefecture.
The total installed capacity of the project is 350 MW, and 97 wind turbines are mainly constructed, including 59 wind turbines with a single capacity of 4 MW and 38 wind turbines with a single capacity of 3 MW
.
The construction period of the project is 12 months
.
The total dynamic investment of the project is 27196749 million yuan, and the total static investment is 26676441000 yuan, of which the project capital is calculated as 20% of the total investment, which is self-financed by the enterprise, and the rest of the funds are borrowed
from commercial banks.
In addition, the Yunnan Provincial Development and Reform Commission emphasized in its approval reply that if all the above-mentioned projects have not started construction for 2 years from the date of the approval decision or the consent to the change decision, and it is necessary to postpone the start of construction, the project is requested to apply to the Provincial Development and Reform Commission for an extension of construction
30 working days before the expiration of the two-year period.
The start of construction can only be postponed once, and the maximum period shall not exceed 1 year
.
Where the State has other provisions on the postponement of the start of construction of a project, follow those provisions
.