Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On the morning of October 12th, the new petroleum coke storage yard project team of Yangzi Petrochemical Company conquered the last main control point and successfully completed the hoisting operation of the second railway reclaimer, marking that the project has completed the main construction and large-scale equipment The hoisting has created conditions for the completion and commissioning at the end of October.
On the morning of October 12th, the new petroleum coke storage yard project team of Yangzi Petrochemical Company conquered the last main control point and successfully completed the hoisting operation of the second railway reclaimer, marking that the project has completed the main construction and large-scale equipment The hoisting has created conditions for the completion and commissioning at the end of October.
At 10 o'clock in the morning on the 12th, after careful preparation and arrangement, a 500-ton large crane drove into the predetermined lifting position, grabbed the ground with four feet, raised the boom, and lifted a 70-ton railway reclaimer from the side.
The new petroleum coke fully enclosed storage yard is an environmental improvement project approved by the headquarters and promised to the government by Yangzi Company.
The project broke ground in March 2019.
The project was carried out while construction was being carried out while production was being carried out.
With the completion of the last main control point of the project, the project has entered the finishing stage of equipment commissioning, single test and joint test, and peripheral auxiliary projects.
The project team stated that it will go all-out day and night, rain or shine, and go all out to ensure that the green petroleum coke transfer center will be completed and put into use at the end of October.