    Home > Chemicals Industry > Petrochemical News > Yangzi Petrochemical Thermal Power Plant completed the purging of ultra-high pressure steam pipeline

    Yangzi Petrochemical Thermal Power Plant completed the purging of ultra-high pressure steam pipeline

    • Last Update: 2021-08-14
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Sinopec News Network News on August 5, after 4 days of ultra-high pressure steam ("SS") pipeline purge work was completed, after confirmation by the project team, project supervision, construction unit, relevant professional departments and other units, green steam supply The SS pipeline in the center was qualified for purging and shooting, which marked the completion of another important node in the project of Yangzi Petrochemical Green Steam Supply Center
    .

    The SS pipeline is the ultra-high pressure steam supplied by Yangzi Petrochemical’s green steam supply center to the company’s olefin plant, which is mainly used to replace the auxiliary boiler of the olefin plant to produce steam
    .
    As the SS pipeline steam will enter the olefin plant turbine, in order to ensure the safe operation of the turbine, it must be purged to ensure the quality of the steam


    .


    In order to ensure the smooth progress of the purging work, the thermal power plant, project team, commissioning and other units formulate the purging plan in advance, and report to the relevant professional department of the company for review
    .
    Since the location of the purged pipeline is on important road sections such as Ethylene Avenue, Yangzi Petrochemical has organized several special meetings to ensure traffic safety during the purging period and reduce the impact of noise


    .


    The thermal power plant has formulated in advance the "Green Steam Supply Center Project SS Steam Pipeline Purge Safety and Environmental Protection Special Plan", "Green Steam Supply Center Project SS Pipeline Purge Safety Measures for the Silencer Area during Steam Purge" and other plans.
    On-site safety measures have been approved by the company's relevant professional departments and projects.
    Units, thermal power plants, olefin plants and other units confirmed that the "three checks and four determinations" of the SS pipeline construction have been confirmed on-site for many times
    .
    In order to control the scope of influence to the minimum, arrange the purge to be carried out at night and non-working days


    .


    The thermal power plant will work with the project team to do a good job in the follow-up commissioning of the green steam supply center project and the start-up of the entire group to ensure the successful start-up of the project


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.