Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
As of 17:00 on May 16, with the completion of the welding of the six construction sections on the same day, the total length of pipeline welding of the natural gas pipeline project of the South Main Line of the Shandong Pipeline Network of the Natural Gas Branch has reached 100.
The natural gas pipeline project of the south trunk line of Shandong pipeline network is 490 kilometers, passing through 17 counties and districts of Rizhao, Linyi, Jining and Heze.
Since the start of construction, the project department of the South Main Line of Shandong Pipeline Network has carried out a labor competition for the construction of the "100 Years of Gifts and Party Building, Helping Clean Winter Olympics" across the board, organizing various departments and 17 participating units to decompose the construction tasks and objectives, and formulate annual implementation plans.
The participating units coordinated the construction organization according to the labor competition node, and increased the input of construction equipment and manpower.
The project quality management department uses methods such as on-site inspection, supervision and supervision, and intelligent pipeline monitoring to strengthen the welding process control, strictly abide by the welding process regulations, implement the pre-weld pre-heating process, and take measures to ensure the inter-layer temperature, which effectively guarantees the welding quality.
The project material supply department speeds up the ordering of pipeline construction steel pipes, strengthens coordination and supervision, and arranges special personnel to expedite delivery to effectively solve the problem of pipe supply in response to the problem that some pipes cannot be supplied normally.
In the next step, the Natural Gas Pipeline Project Department of the South Main Line of Shandong Pipeline Network will speed up the construction of the project in accordance with the labor competition plan, and present more outstanding achievements to the 100th anniversary of the founding of the party.