    Tianjin LNG (Phase II) project completed the pouring construction of the bottom cap of the storage tank

    • Last Update: 2021-07-30
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Recently, after 52 hours of continuous operation by the employees of the Fourth Construction Company, Tianjin LNG (Phase II) project successfully completed the one-time pouring of 7944 cubic meters of low-temperature concrete on the bottom cap of No.
    8 storage tank
    .

    In order to ensure the smooth completion of the pouring of the No.
    8 storage tank bottom cap of the Tianjin LNG (Phase II) project, during the pouring construction, the participating employees overcome the constraints of the narrow site and the limited placement of tank trucks and pumps.
    The project department of the Fourth Construction Company did A large amount of full and comprehensive preparations, combined with the experience of No.
    5 and No.
    6 storage tanks, formulated detailed construction plans, discussed and exchanged with the owners and supervisors, optimized the construction plan, refined safeguard measures, clarified the division of responsibilities of personnel at all levels, and implemented the construction equipment Resources to ensure implementation as planned
    .

    Several large-scale concrete pump trucks with a height of 65 meters were operating at the same time, and the construction personnel performed their duties, fighting day and night, and fully coordinated, and the construction of the platform pouring was successfully completed as planned
    .


    At present, the storage tank area No.


    While the construction of the storage tanks has set off a great upsurge, the wharf area that will be put into use in November this year is also under construction
    .


    Up to now, 88% of the civil construction of the terminal’s power distribution room has been completed, the main formwork construction of the control manufacturing room has been completed, the steel bar lashing has been completed 65%, the pipe pier foundation has been completed, and the pipe prefabrication has been installed with a diameter of 11411.


    In the case of various difficulties encountered in the construction of the wharf trestle, the project department of the Fourth Construction Company actively overcomes the various difficulties in the construction, timely adjusts the construction plan, interleaves the work before the construction, and makes effective use of the temporary construction work platform channel of the wharf at night Staggered peak construction and other methods, rationally arrange the construction of various specialties to be carried out in an orderly manner to ensure that the project progress in the area is implemented steadily as planned


      (Qu Zhaogui Gao Xin)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.