    Home > Chemicals Industry > Rubber Plastic News > Tianjin Bohua DMTO plant with an annual output of 1.8 million tons is handed over!

    Tianjin Bohua DMTO plant with an annual output of 1.8 million tons is handed over!

    • Last Update: 2022-08-25
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    ●Tianjin Bohua's 1.
    8 million tons/year methanol-to-olefins plant has been handed over, which is the second large-scale MTO plant newly built this year

    ●The 12th Coal-to-Olefin and High-end Chemicals Forum will be held in Yinchuan, Ningxia on October 20-21.
    The meeting will focus on the coal/methanol-to-olefin project and capacity outlook

    ●The conference will visit Ningxia Baofeng Energy's 1.
    2 million tons/year coal-to-olefins world-class plant located in Ningdong Energy and Chemical Base

    On September 26, 2020, the handover ceremony of the 1.
    8 million tons/year methanol-to-olefins plant of Tianjin Bohua Chemical Development Co.
    , Ltd.
    's "two chemical industry" relocation and renovation project was held


    .


    The “two modernizations” relocation and reconstruction project of Bohua Chemical Industry Co.
    , Ltd.
    is a key project in Tianjin and an important industrial project for building a world-class chemical new material base in Tianjin Nangang Industrial Zone, with a total investment of 29.
    4 billion yuan and a total land area of ​​3.
    05 square kilometers


    .


    The two-phase construction units of the project include: 2×1.
    8 million tons/year methanol-to-olefin (MTO) units, 300,000 tons/year polyethylene (PE) units, 2×300,000 tons/year polypropylene (PP) units, 600,000 tons/year polypropylene (PP) units ton/year ionic membrane caustic soda, 800,000 tons/year polyvinyl chloride (PVC) plant, 60,000 tons/year ethylene oxide (EO), 40,000 tons/year surfactant (EO, AEO) and water reducer (PEG) unit, 200,000 tons/year propylene oxide co-production 450,000 tons/year styrene (PO/SM) unit, 100,000 tons/year polyether PPG), 30,000 tons/year polymer polyol (POP) ) device, 100,000 tons/year hydrogen peroxide device


    .


    The 1.
    8 million t/a methanol-to-olefins plant of the first phase of the project adopts the DMTO-II methanol-to-olefins proprietary technology of Dalian Chemical Institute, and was contracted by Luoyang Engineering Company.
    The construction started on July 18, 2018


    .


    ASIACHEM's "China Coal-to-Olefin Annual Report 2020" shows that Tianjin Bohua's 1.
    8 million tons/year methanol-to-olefins plant is the second large-scale MTO plant newly built in 2020


    .


    Recent progress of Tianjin Bohua project

    On August 17, Tianjin Bohua Chemical Development Co.
    , Ltd.
    completed the dual-circuit power transmission of the 220kV substation on Tengfei Road, marking the synchronization of the key nodes of the public works supporting the relocation and reconstruction project of Bohua Chemical Industry Co.
    , Ltd.
    Completion provides a strong guarantee for the project to enter the mid-term delivery stage in September and to achieve the mid-term delivery of all installations by the end of the year


    .


    It was learned on September 21 that the prefabrication of the pressure-guiding pipe of the DMTO unit of the DMTO unit of the 1.
    8 million tons/year methanol-to-olefins unit of the Tianjin Bohua Chemical and Chemicals Relocation Project undertaken by Sinopec Sijian Electric Instrument Company is nearing completion, and the total prefabrication has been completed.
    90%


    .


    It was learned on September 24 that the five towers of the Tianjin Bohua hydrogen peroxide project, which was installed and constructed by China Construction Group, were successfully hoisted into place


    .


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.