Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
24 wind turbines operate around the clock on mountaintops at an average altitude of more than 1,100 meters, delivering powerful electricity
.
From April 2015 to May 20 this year, the first phase of the Yangcun wind power project in Rong County, China Resources New Energy has sent 140 million kilowatt-hours of electricity, achieving an output value of 86.
8 million yuan
.
The second phase of the project has begun to install capacity, and it is expected to be connected to the grid by the end of the
year.
The first phase of the wind power project in Yangcun, Rong County, with a total investment of 500 million yuan, installed 24 wind turbines with a total installed capacity of 48,000 kilowatts, entered the construction
site in early November 2013.
In order to ensure the smooth progress of the project, the Rong County government and relevant departments arranged a large amount of manpower and material resources, widely publicized and mobilized the masses, and solved the problems of
land acquisition, land lease and relocation in a short period of time.
The project is located in a remote mountainous area, the project owner and the majority of engineering technicians and workers have overcome the difficulties of high altitude, rainy days, heavy fog, inconvenient transportation, etc.
, on October 15, 2014, the first phase of the wind power project installed the first fan
.
In April 2015, all 24 units were installed and connected to the grid for power generation
.
For more than a year, wind turbines have been operating normally, reaching the expected
annual power generation of 120 million kWh.
At the beginning of 2015, the second phase of the wind power project in Yangcun, Rong County started construction
.
The project invested 490 million yuan to install 19 wind turbines with a total installed capacity of 38,000 kilowatts
.
At present, 34 kilometers of access roads have been built, 19 wind turbine foundation platforms have been watered, two wind turbines have been installed and all transmission and transformation grid lines have been erected
.
According to the person in charge of the project, the remaining 17 wind turbines will be installed and connected to the grid by
the end of December this year.
By then, the annual power generation capacity of Yangcun Wind Power Project in Rong County of China Resources New Energy will reach more than 200 million kWh, achieving an output value of 130 million yuan, becoming the largest green new energy project
in Yulin City.
24 wind turbines operate around the clock on mountaintops at an average altitude of more than 1,100 meters, delivering powerful electricity
.
From April 2015 to May 20 this year, the first phase of the Yangcun wind power project in Rong County, China Resources New Energy has sent 140 million kilowatt-hours of electricity, achieving an output value of 86.
8 million yuan
.
The second phase of the project has begun to install capacity, and it is expected to be connected to the grid by the end of the
year.
The first phase of the wind power project in Yangcun, Rong County, with a total investment of 500 million yuan, installed 24 wind turbines with a total installed capacity of 48,000 kilowatts, entered the construction
site in early November 2013.
In order to ensure the smooth progress of the project, the Rong County government and relevant departments arranged a large amount of manpower and material resources, widely publicized and mobilized the masses, and solved the problems of
land acquisition, land lease and relocation in a short period of time.
The project is located in a remote mountainous area, the project owner and the majority of engineering technicians and workers have overcome the difficulties of high altitude, rainy days, heavy fog, inconvenient transportation, etc.
, on October 15, 2014, the first phase of the wind power project installed the first fan
.
In April 2015, all 24 units were installed and connected to the grid for power generation
.
For more than a year, wind turbines have been operating normally, reaching the expected
annual power generation of 120 million kWh.
At the beginning of 2015, the second phase of the wind power project in Yangcun, Rong County started construction
.
The project invested 490 million yuan to install 19 wind turbines with a total installed capacity of 38,000 kilowatts
.
At present, 34 kilometers of access roads have been built, 19 wind turbine foundation platforms have been watered, two wind turbines have been installed and all transmission and transformation grid lines have been erected
.
According to the person in charge of the project, the remaining 17 wind turbines will be installed and connected to the grid by
the end of December this year.
By then, the annual power generation capacity of Yangcun Wind Power Project in Rong County of China Resources New Energy will reach more than 200 million kWh, achieving an output value of 130 million yuan, becoming the largest green new energy project
in Yulin City.