    The world's largest single set of aromatics production capacity has achieved intermediate delivery

    • Last Update: 2022-11-07
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On the morning of July 30, the handover ceremony of the 2.
    6 million t/a aromatics complex of PetroChina Guangdong Petrochemical Refining and Chemical Integration Project located in the Binhai New Area of ​​Jieyang was held on site

    .
    The device is currently the world's largest aromatics plant with the largest single production capacity.
    It has the advantages of high intelligence and low energy consumption.
    It is the core device of the Guangdong Petrochemical Project.
    After it is completed and put into operation, it will greatly reduce China's dependence on imported aromatics and improve the self-protection of raw materials.
    ability

    .

    The aromatics complex delivered this time was contracted by China Kunlun Engineering Co.
    , Ltd.
    EPC, and the Seventh Construction Company of China Petroleum Engineering Construction Co.
    , Ltd.
    , China Eneng Group First Engineering Bureau Co.
    , Ltd.
    and other units are responsible for the construction

    .
    Covering a total area of ​​nearly 100,000 square meters, there are 7 sets of thousand-ton equipment, 4,330 cast-in-place piles, 42,000 tons of concrete pouring, 21,000 tons of steel structure installation, 810,000 inches of welding joints for process pipes, 250,000 square meters of steel structure fire protection, and thermal insulation.
    With 10,000 cubic meters, a total of 1,000 kilometers of cables, and 843 pressure test packages, it is a veritable world-class "aromatic giant"

    .

    Since the start of construction in April 2020, all participating units have carried out scientific organization, careful planning, and strict deployment of the construction, overcoming many difficulties such as a four-and-a-half-month late start, tight working space, and the impact of the epidemic
    .
    Guangdong Petrochemical, Kunlun Engineering, Engineering Construction Company and China Aneng grass-roots party branch have actively joined together to set up a number of teams such as the "dressing and hat" party member commando team for the raffinate tower of the aromatic hydrocarbon joint plant, taking the initiative to act and explore actively.
    On April 17, 2021, the largest raffinate tower in Asia with a weight of 4,606 tons was successfully hoisted in one fell swoop, creating 3 domestic items of "the first lifting weight, the first gantry main crane, and the first 4,000-ton auxiliary crane".
    Records in the field of hoisting

    .
    Thanks to the efforts of all parties involved in the construction, the aromatics complex finally ushered in the day of the handover, and achieved 12.
    8 million safe production man-hours

    .

    The CCCC of the aromatics complex marks a step closer to the commissioning of the Guangdong Petrochemical refining and chemical integration project
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.