Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Recently, the modular hoisting tasks of 9 towers of the 600,000-ton/year styrene plant of Gulei Refinery and Chemical Engineering Co.
, Ltd.
have been completed
.
The total length of the ethylbenzene tower C-105 attached tower pipeline is 176 meters and weighs 23.
98 tons
.
It is understood that the two largest towers among the nine styrene towers are: high-pressure crude styrene tower C-218 and low-pressure crude styrene tower C-202
.
Shijian Company actively responded to the construction strategy requirements of "one site, two construction sites" and "space for time" of Gulei Petrochemical Project Management Department, overcame the influence of high temperature, heat, small site and other factors, optimized the construction plan, strengthened safety control and operation.
Risk analysis is carried out in advance, and hidden dangers are checked to ensure safe, high-quality and efficient construction
.
Shijian Gulei Refining and Chemical Engineering Project Department organized scientifically in terms of personnel arrangement, mechanical coordination, planning measures, etc.
to ensure the smooth completion of the modular hoisting task, creating conditions for the next pipeline installation
.