    The total progress is about 93.96% completed!

    • Last Update: 2022-10-15
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    The total progress of Hainan Refinery's 1 million tons of ethylene project is 93.
    96%

    The total progress of Hainan Refinery's 1 million tons of ethylene project is 93.
    96%

    The total progress of Hainan Refinery's 1 million tons of ethylene project is 93.
    96%

    The total progress of Hainan Refinery's 1 million tons of ethylene project is 93.
    96%

    Hainan Refining & Chemical's 1 million tons/year ethylene and refining expansion project is a key project of Hainan Province and Sinopec, with a total investment of more than 28 billion yuan
    .
    At present, the overall progress of the project is about 93.
    96% completed

    .
    After it is completed and put into operation, it is expected to directly drive more than 100 billion yuan of downstream industries, and it will become a new engine for the future development of Hainan Province

    .

    About 14,000 workers are in full swing at the site of Hainan Refinery's 1 million tons/year ethylene and oil refining reconstruction and expansion project
    .
    According to reports, the overall progress of the project has been completed by about 93.
    96%, the main projects of various public works have been handed over in succession, the main production devices have entered the peak period of electrical and instrument installation, and each link is steadily advancing according to the established time node

    .

    About 14,000 workers are in full swing at the site of Hainan Refinery's 1 million tons/year ethylene and oil refining reconstruction and expansion project
    .
    According to reports, the overall progress of the project has been completed by about 93.
    96%, the main projects of various public works have been handed over in succession, the main production devices have entered the peak period of electrical and instrument installation, and each link is steadily advancing according to the established time node

    .

    According to Gong Yaohui, the chief construction dispatcher of the ethylene project, in order to meet the node target requirements of "6.
    30" and "9.
    30", all functional departments work together to formulate a specific CCCC plan according to the actual situation

    .
    Last month, the project has entered the formal "three investigations and four determinations" ahead of schedule, to ensure that the problems are checked in advance, and to ensure that the time nodes of subsequent production and material delivery are completed on schedule

    .

    All 11 major public works projects have been handed over

    On May 23, Hainan Refinery and Chemical's ethylene project held a signing ceremony for the centralized delivery of public works devices.
    Six major projects including the power center constructed by Ningbo Engineering Company were officially signed by CCCC, marking that 11 Hainan ethylene projects were contracted by the company's EPC.
    The main items of public works are all completed in mid-term handover

    .

    The 1 million tons/year ethylene and oil refining reconstruction and expansion project of Hainan Refinery is a key project included in the national petrochemical industry plan.
    It is also a key project for Sinopec to promote the development strategy of "two three years and two ten years" to build a world-class energy and chemical company.
    support project

    .
    After the project is put into operation, it will greatly promote the development of downstream industries such as advanced agriculture, green chemical industry, tourism and health, improve the competitiveness of Sinopec in the international market, ensure national energy security, drive the economic development of Hainan Province and help the construction of Hainan Free Trade Port

    .

    According to Gong Yaohui, the chief construction dispatcher of the ethylene project, in order to meet the node target requirements of "6.
    30" and "9.
    30", all functional departments work together to formulate a specific CCCC plan according to the actual situation

    .
    Last month, the project has entered the formal "three investigations and four determinations" ahead of schedule, to ensure that the problems are checked in advance, and to ensure that the time nodes of subsequent production and material delivery are completed on schedule

    .

    All 11 major public works projects have been handed over

    On May 23, Hainan Refinery and Chemical's ethylene project held a signing ceremony for the centralized delivery of public works devices.
    Six major projects including the power center constructed by Ningbo Engineering Company were officially signed by CCCC, marking that 11 Hainan ethylene projects were contracted by the company's EPC.
    The main items of public works are all completed in mid-term handover

    .

    The 1 million tons/year ethylene and oil refining reconstruction and expansion project of Hainan Refinery is a key project included in the national petrochemical industry plan.
    It is also a key project for Sinopec to promote the development strategy of "two three years and two ten years" to build a world-class energy and chemical company.
    support project

    .
    After the project is put into operation, it will greatly promote the development of downstream industries such as advanced agriculture, green chemical industry, tourism and health, improve the competitiveness of Sinopec in the international market, ensure national energy security, drive the economic development of Hainan Province and help the construction of Hainan Free Trade Port

    .

    According to Gong Yaohui, the chief construction dispatcher of the ethylene project, in order to meet the node target requirements of "6.
    30" and "9.
    30", all functional departments work together to formulate a specific CCCC plan according to the actual situation

    .
    Last month, the project has entered the formal "three investigations and four determinations" ahead of schedule, to ensure that the problems are checked in advance, and to ensure that the time nodes of subsequent production and material delivery are completed on schedule

    .

    All 11 major public works projects have been handed over

    On May 23, Hainan Refinery and Chemical's ethylene project held a signing ceremony for the centralized delivery of public works devices.
    Six major projects including the power center constructed by Ningbo Engineering Company were officially signed by CCCC, marking that 11 Hainan ethylene projects were contracted by the company's EPC.
    The main items of public works are all completed in mid-term handover

    .

    The 1 million tons/year ethylene and oil refining reconstruction and expansion project of Hainan Refinery is a key project included in the national petrochemical industry plan.
    It is also a key project for Sinopec to promote the development strategy of "two three years and two ten years" to build a world-class energy and chemical company.
    support project

    .
    After the project is put into operation, it will greatly promote the development of downstream industries such as advanced agriculture, green chemical industry, tourism and health, improve the competitiveness of Sinopec in the international market, ensure national energy security, drive the economic development of Hainan Province and help the construction of Hainan Free Trade Port

    .

    According to Gong Yaohui, the chief construction dispatcher of the ethylene project, in order to meet the node target requirements of "6.
    30" and "9.
    30", all functional departments work together to formulate a specific CCCC plan according to the actual situation

    .
    Last month, the project has entered the formal "three investigations and four determinations" ahead of schedule, to ensure that the problems are checked in advance, and to ensure that the time nodes of subsequent production and material delivery are completed on schedule

    .

    All 11 major public works projects have been handed over

    All 11 major public works projects have been handed over

    All 11 major public works projects have been handed over

    All 11 major public works projects have been handed over

    All 11 major public works projects have been handed over
    On May 23, Hainan Refinery and Chemical's ethylene project held a signing ceremony for the centralized delivery of public works devices.
    Six major projects including the power center constructed by Ningbo Engineering Company were officially signed by CCCC, marking that 11 Hainan ethylene projects were contracted by the company's EPC.
    The main items of public works are all completed in mid-term handover

    .

    On May 23, Hainan Refinery and Chemical's ethylene project held a signing ceremony for the centralized delivery of public works devices.
    Six major projects including the power center constructed by Ningbo Engineering Company were officially signed by CCCC, marking that 11 Hainan ethylene projects were contracted by the company's EPC.
    The main items of public works are all completed in mid-term handover

    .

    On May 23, Hainan Refinery and Chemical's ethylene project held a signing ceremony for the centralized delivery of public works devices.
    Six major projects including the power center constructed by Ningbo Engineering Company were officially signed by CCCC, marking that 11 Hainan ethylene projects were contracted by the company's EPC.
    The main items of public works are all completed in mid-term handover

    .

    The 1 million tons/year ethylene and oil refining reconstruction and expansion project of Hainan Refinery is a key project included in the national petrochemical industry plan.
    It is also a key project for Sinopec to promote the development strategy of "two three years and two ten years" to build a world-class energy and chemical company.
    support project

    .
    After the project is put into operation, it will greatly promote the development of downstream industries such as advanced agriculture, green chemical industry, tourism and health, improve the competitiveness of Sinopec in the international market, ensure national energy security, drive the economic development of Hainan Province and help the construction of Hainan Free Trade Port

    .
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.