    On March 16, the civil engineering of Sinopec Tianjin Nangang Ethylene Project started, marking the official entry of the cluster project into the construction stage
    .

    On the same day, the “National Four Sets” unit of Tianjin Nangang Ethylene Project constructed by Sinopec Tenth Construction Company started construction
    .
    Relevant persons in charge of Sinopec Tianjin Branch, Sinopec Guangzhou Engineering Co.
    , Ltd.
    , Zhenhai Petrochemical Engineering Co.
    , Ltd.
    , Hubei Xingsifang Engineering Management Co.
    , Ltd.
    , Beijing Huaxia Petrochemical Engineering Supervision Co.
    , Ltd.
    and employees of the company's Tianjin Engineering Project Department participated in the start of construction ceremony
    .

    Tianjin Nangang Ethylene Project is a key construction project of the group company.
    In this project, the company has undertaken the construction tasks of 11 units
    .
    Among them, the "National Four" includes 600,000 tons/year pyrolysis gasoline hydrogenation unit, 380,000 tons/year aromatics extraction unit, 150,000 tons/year butadiene extraction unit, 13/40,000 tons/year MTBE/year For the butene-1 plant, the project construction is faced with many unfavorable factors, such as a wide range of points, complex geological conditions, and difficulty in safety management and control
    .

    The 1.
    2 million tons/year ethylene project in Tianjin Nangang has a total investment of 60.
    3 billion yuan.
    It is a major project to promote the national strategy of coordinated development of Beijing, Tianjin and Hebei.
    It will be officially launched in May 2021
    .

    The project cluster consists of 11 projects, including Tianjin Nangang Ethylene and Downstream High-end New Material Industry Cluster, Beijing Chemical Research Institute Pilot Base, Great Wall Lubricant, Catalyst Production Base, LNG Expansion, Science Experiment Base of the Academy of Stone Science, and Achievement Transformation Center of the Academy of Engineering , photovoltaic new energy, petrochemical e-trade platform and other key projects
    .

    As the leader of the project cluster, Nangang Ethylene Project takes the 1.
    2 million tons/year ethylene plant as the leader, aims to be the world leader, fills the domestic gap, replaces imports, and extends the industrial chain to build ultra-high molecular weight, α-olefin, ALL-PE, ABS, POE , HDPE and other 12 sets of high-end new material devices
    .

    It is understood that Nangang Ethylene is expected to be completed in 2023, and the project cluster is expected to be completed in 2025
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.