    The total investment is 2.1 billion, and the construction of the 200,000-ton glass fiber project in Hebei is accelerated!

    • Last Update: 2022-08-22
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    A few days ago, dozens of construction workers were busy at the construction site of the 200,000-ton glass fiber production line project of Jizhong Energy Co.
    , Ltd.
    , a key project in Hebei Province


    .


    The 200,000-ton glass fiber production line project under construction is located in Shahe Economic Development Zone, Xingtai City, Hebei Province.
    The main products are high-strength glass fiber products


    .


    After the Spring Festival holiday, the project was originally scheduled to resume work on January 30 this year, but due to the impact of the epidemic, it was postponed to February 10


    .


    The total investment of the whole project is 2.
    1 billion yuan, and it is planned to be completed in two phases and two years


    .


    At the construction site, dozens of construction workers wearing masks are working in different areas


    .


    Due to the new crown pneumonia epidemic, the personnel, materials, equipment and other aspects required for the project construction have been greatly affected


    .


    Wang Dongjie, deputy director of the Preparatory Construction Office, said that they will continue to follow the requirements of epidemic prevention and control, and on the premise of ensuring effective prevention and control, combined with the actual situation of the current construction site, to reorganize and optimize the work plan, and further increase the number of construction personnel on duty.
    Make sure the project is completed on time


    .


    Zhang Jiyun, director of the preparatory construction department, said that in the next step, they will follow the overall requirements of "high starting point, high standard, high quality, and high efficiency", while effectively preventing and controlling the epidemic, they will make every effort to speed up the project construction, ensure that the ignition is put into production on schedule, and provide enterprises and enterprises as soon as possible.
    Contribute to local social and economic development


    .


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.