    On May 6, You Qiangqiang, Deputy Secretary of the Party Committee, Director and General Manager of Xinjiang Energy and Chemical Company, led a team to China Tianchen Engineering Co.
    , Ltd.
    to participate in the general design and start-up meeting of the Zhundong Wucaiwan Coal-to-Olefin Project with an annual output of 800,000 tons

    .

    The meeting began at 9:15 am on May 7
    .
    At the meeting, you emphasized the situation of Xinjiang Energy and Chemical Company and the coal-to-olefin project.
    He said that the coal-to-olefin project with an annual output of 800,000 tons is a key project planned and invested by Shandong Energy in Xinjiang, and it is the integration of the Zhundong coal chemical industry of Xinjiang Energy and Chemical Company.
    An important component of the project and an important support for future development

    .
    The two sides have cooperated for a long time and have a deep friendship.
    In the following overall design work, as a construction unit, Xinjiang Nenghua Company will go all out to provide various materials in a timely and accurate manner, and do a good job in various guarantees

    .

    Jiao Zaiyue, Deputy Secretary of the Party Committee and General Manager of China Tianchen Engineering Co.
    , Ltd.
    , said in his welcome speech that the two sides have formed a profound friendship in the long-term cooperation, and will continue to strengthen cooperation in the next step to ensure the completion of the overall design of coal-to-olefins with high quality.
    various jobs

    .
    At the meeting, Gao Zhihui, the design manager of China Tianchen Engineering Co.
    , Ltd.
    , reported the overall design start-up report, and the two parties confirmed the design basis and unified regulations for the overall design

    .

    It is reported that from the afternoon of May 7 to 8, the two parties will also discuss the specific content of the overall design of the project
    .

    On April 17, Xinjiang Shanneng Chemical Co.
    , Ltd.
    announced the winning bid for the overall design of the 800,000-ton-per-year coal-to-olefin project in Zhundong Wucaiwan

    .
    Winning bidder: China Tianchen Engineering Co.
    , Ltd.

    Project Overview

    Project Overview

    Construction site: West side of Shenqi Road, Wucaiwan No.
    4 open-pit mine, Huoshaoshan Industrial Park, Wucaiwan Mining Area, Zhundong Economic and Technological Development Zone, Xinjiang

    .

    Construction scale and overview: The project uses Wucaiwan No.
    4 open-pit coal as raw material, and produces MTO-grade methanol (intermediate product) through pulverized coal pressurized gasification, transformation and heat recovery, low-temperature methanol washing, and methanol synthesis; Polymerization grade ethylene and polymerization grade propylene monomers are obtained by separation of MTO and olefin; ethylene is polymerized to produce polyethylene products; propylene is polymerized to produce polypropylene products

    .
    The process technology to be selected for the main production units of this project is close to or reaches the current international advanced level

    .

    The main process units of this project include: air separation unit, gasification unit, purification unit, methanol unit, sulfur recovery unit, MTO unit (four-cycle refining containing carbon), olefin separation unit, polyethylene unit, polypropylene unit,
    etc.

    The public works of this project include: power station, whole plant water supply and drainage engineering (including fire water system), sewage treatment, reclaimed water reuse, concentrated evaporation and crystallization, whole plant power supply and distribution, whole plant telecommunications, whole plant external pipes, intermediate products Tank farm and liquid material vehicle loading and unloading station, olefin tank farm, flare system, underground pipe network, air compressor station, heat exchange station, storage and transportation system, off-site engineering,
    etc.

    Auxiliary projects include but are not limited to: the general plan transportation of the whole plant, the fire protection of the whole plant, the gas defense system, the central control room, the central laboratory (environmental monitoring station), the inspection and maintenance center, the hazardous chemical warehouse, the temporary warehouse for hazardous waste, the miscellaneous Salt temporary storage warehouse, whole plant information management system, comprehensive office building, canteen, shift dormitory, R&D center, PP and PE finished product warehouse, etc.
    and temporary facilities of the whole plant

    .

    The supporting Wucaiwan No.
    4 open-pit mine is integrated and constructed simultaneously with the project.
    The power supply, water supply, heating, production and domestic sewage reception and treatment of the No.
    4 open-pit mine should be considered in the design of the project, and the office building, dormitory, and canteen should be considered.
    And other living facilities are shared to achieve the optimization of investment

    .
    The specific requirements and conditions of the No.
    4 open-pit mine (including power supply, water supply, heating, production and domestic sewage treatment, etc.
    , as well as office, dormitory, canteen and other living facilities needs) shall be provided by the tenderee alone

    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Related Articles

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.