    The three submarine cables in Yangjiang, Guangdong are about to be laid

    • Last Update: 2022-11-20
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On February 23, the last of the three submarine cables in Yangjiang City, Guangdong Province will be laid on the evening of February 24, and the entire project will be completed
    before the summer tourist peak.

    Guan Xunjian, deputy director of the Infrastructure Department of Yangjiang Power Supply Bureau, introduced that laying submarine cables to build the third 110 kV line, in the case of overhead line power outages, it can also basically meet the power supply demand
    of Hailing Island.
    It is understood that the total length of the overhead part of the project is 19.
    3 kilometers, and the total length of the submarine cable is about 3.
    3 kilometers, and the cable will be buried by the buried plow of the construction ship, and the cable will be buried 1.
    5 meters
    below the seabed.
    At present, 2 cables have landed smoothly, the third cable will land on the evening of the 24th, and the whole project will be completed
    before the peak of tourism this summer.

     

    On February 23, the last of the three submarine cables in Yangjiang City, Guangdong Province will be laid on the evening of February 24, and the entire project will be completed
    before the summer tourist peak.

    Submarine cables

    Guan Xunjian, deputy director of the Infrastructure Department of Yangjiang Power Supply Bureau, introduced that laying submarine cables to build the third 110 kV line, in the case of overhead line power outages, it can also basically meet the power supply demand
    of Hailing Island.
    It is understood that the total length of the overhead part of the project is 19.
    3 kilometers, and the total length of the submarine cable is about 3.
    3 kilometers, and the cable will be buried by the buried plow of the construction ship, and the cable will be buried 1.
    5 meters
    below the seabed.
    At present, 2 cables have landed smoothly, the third cable will land on the evening of the 24th, and the whole project will be completed
    before the peak of tourism this summer.

     

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.