    The third wind farm of the second phase of the Three Gorges Pakistan Wind Power Project was put into operation 102 days ahead of schedule

    • Last Update: 2022-12-27
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On June 9, the third wind farm of the Three Gorges Pakistan Wind Power Phase II Project received the commercial operation certificate issued by the Pakistan Central Power Procurement Center, and officially entered commercial operation from 0:00 on the same day, 102 days
    earlier than the time stipulated in the power purchase agreement.

    It is reported that the commissioning and testing of the wind power project lasted more than two months
    .
    During the whole commissioning process, from the Pakistani government to the engineers, from the project company to the general contractor, all parties worked together and kept pace with each other, and all the work progressed smoothly and achieved the set goals
    of the project.
    At present, the unit is running smoothly, and the data of the booster station is normal
    .

    At the same time, the second wind farm of the second phase of the Pakistan wind power project has also completed all the pre-trial operation preparations, and will enter 168 hours of trial operation in the near future, and is scheduled to achieve commercial operation
    by the end of this month.
    At that time, the second phase of Pakistan's wind power project will be fully put into operation, becoming the first "China-Pakistan Economic Corridor Project"
    put into operation by the Three Gorges Group.
    The project can provide 300 million kilowatt-hours of clean energy to Pakistan every year, which will greatly improve its power shortage
    .

    On June 9, the third wind farm of the Three Gorges Pakistan Wind Power Phase II Project received the commercial operation certificate issued by the Pakistan Central Power Procurement Center, and officially entered commercial operation from 0:00 on the same day, 102 days
    earlier than the time stipulated in the power purchase agreement.

    Wind power

    It is reported that the commissioning and testing of the wind power project lasted more than two months
    .
    During the whole commissioning process, from the Pakistani government to the engineers, from the project company to the general contractor, all parties worked together and kept pace with each other, and all the work progressed smoothly and achieved the set goals
    of the project.
    At present, the unit is running smoothly, and the data of the booster station is normal
    .

    At the same time, the second wind farm of the second phase of the Pakistan wind power project has also completed all the pre-trial operation preparations, and will enter 168 hours of trial operation in the near future, and is scheduled to achieve commercial operation
    by the end of this month.
    At that time, the second phase of Pakistan's wind power project will be fully put into operation, becoming the first "China-Pakistan Economic Corridor Project"
    put into operation by the Three Gorges Group.
    The project can provide 300 million kilowatt-hours of clean energy to Pakistan every year, which will greatly improve its power shortage
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.