    The spread of the new crown epidemic has delayed the construction of 13 GW of coal power projects worldwide

    • Last Update: 2023-01-02
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Global coal power plant development has declined for the fourth consecutive year in 2019, while construction of a total of 13 gigawatts (GW) of capacity has been delayed
    so far this year due to the coronavirus, according to a joint study by multiple environmental groups around the world.

    An annual survey of coal-fired power plant pipeline projects around the world by Global Energy Monitor, Greenpeace International, Sierra Club and the Energy and Clean Air Research Center showed a 16 percent
    drop in capacity under construction and development last year.

    This year, construction of 15 coal plants with a total capacity of 13 GW has been delayed
    so far due to labor or supply chain issues related to the coronavirus outbreak.

    Even with an overall decline in coal-fired power plant development in 2019, the world is still on track with the drastic cuts in coal-fired power generation needed to limit global warming
    , the report said.

    Scientists say coal use needs to be reduced by 80 percent by 2030 to keep global warming below
    1.
    5 degrees Celsius.

    Globally, coal power generation fell 3% in 2019 compared to 2018, the biggest decline since 1990
    .

    New coal-fired power plant developers will face increasingly tough conditions
    due to investment restrictions by banks and insurance companies and government commitments to phase out coal.

    Global coal power plant development has declined for the fourth consecutive year in 2019, while construction of a total of 13 gigawatts (GW) of capacity has been delayed
    so far this year due to the coronavirus, according to a joint study by multiple environmental groups around the world.

    An annual survey of coal-fired power plant pipeline projects around the world by Global Energy Monitor, Greenpeace International, Sierra Club and the Energy and Clean Air Research Center showed a 16 percent
    drop in capacity under construction and development last year.

    This year, construction of 15 coal plants with a total capacity of 13 GW has been delayed
    so far due to labor or supply chain issues related to the coronavirus outbreak.

    Even with an overall decline in coal-fired power plant development in 2019, the world is still on track with the drastic cuts in coal-fired power generation needed to limit global warming
    , the report said.

    Scientists say coal use needs to be reduced by 80 percent by 2030 to keep global warming below
    1.
    5 degrees Celsius.

    Globally, coal power generation fell 3% in 2019 compared to 2018, the biggest decline since 1990
    .

    New coal-fired power plant developers will face increasingly tough conditions
    due to investment restrictions by banks and insurance companies and government commitments to phase out coal.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.