Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On September 15, 2018, the second-ring steam generator of Tianwan Unit 5 was hoisted into place, which was another main equipment installation completed after the lifting of the third-ring main pump in September, and the Tianwan Nuclear "Core" Youth Commando Team made new achievements in the installation of the main equipment of Unit 5!
After a series of work such as flipping ring installation, seismic strip removal, horizontal support ring and lifting device installation, connecting slings, flipping bracket installation, etc.
, the second ring steam generator successfully completed the flipping and hoisting in place, and the lifting operation process was completed
3 days earlier than the first steam generator.
In order to successfully complete the flipping and hoisting of the second ring steam generator of Unit 5, the Tianwan Project Department of the company organized the Nuclear Power Institute, Jiangsu Nuclear Power Co.
, Ltd.
, China Nuclear Engineering Consulting Company and CNNC No.
23 Company to hold a feedback meeting on the lifting experience of the first evaporator of Unit 5 in advance, modified and improved the scheme for the problems that occurred in the process of lifting and putting the first evaporator in place, and organized the supervision and installation of the prerequisite inspection and the empty hook simulation test before this lifting to ensure the smooth completion of this lifting operation
。
On September 15, 2018, the second-ring steam generator of Tianwan Unit 5 was hoisted into place, which was another main equipment installation completed after the lifting of the third-ring main pump in September, and the Tianwan Nuclear "Core" Youth Commando Team made new achievements in the installation of the main equipment of Unit 5!
Unit
After a series of work such as flipping ring installation, seismic strip removal, horizontal support ring and lifting device installation, connecting slings, flipping bracket installation, etc.
, the second ring steam generator successfully completed the flipping and hoisting in place, and the lifting operation process was completed
3 days earlier than the first steam generator.
In order to successfully complete the flipping and hoisting of the second ring steam generator of Unit 5, the Tianwan Project Department of the company organized the Nuclear Power Institute, Jiangsu Nuclear Power Co.
, Ltd.
, China Nuclear Engineering Consulting Company and CNNC No.
23 Company to hold a feedback meeting on the lifting experience of the first evaporator of Unit 5 in advance, modified and improved the scheme for the problems that occurred in the process of lifting and putting the first evaporator in place, and organized the supervision and installation of the prerequisite inspection and the empty hook simulation test before this lifting to ensure the smooth completion of this lifting operation
。