    The second phase of Jiangxi Hongmen photovoltaic project successfully achieved the goal of grid connection

    • Last Update: 2022-11-22
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    At 16:45 on June 26, the Hongmen Phase II photovoltaic project of Jiangxi Company was successfully connected to the grid after
    24 hours of no-load trial operation.

    Hongmen Phase II photovoltaic is the expansion project of Hongmen photovoltaic power station of State Power Investment Jiangxi Company, since April 7 started construction, the construction scale is 7MWp, there are six 1.
    166MWp solar module arrays, the use of 265Wp solar photovoltaic modules, fixed installation mode, through the first phase of the photovoltaic project 35kV collector line into the line interval on the Internet, after the project is put into operation, the average annual utilization hours are about 891.
    25 hours, the design annual average power generation is 6.
    2976 million kWh
    .
    The grid-connected power generation of the project has added a new stroke
    to the company's energy development.


    At 16:45 on June 26, the Hongmen Phase II photovoltaic project of Jiangxi Company was successfully connected to the grid after
    24 hours of no-load trial operation.

    photovoltaic

    Hongmen Phase II photovoltaic is the expansion project of Hongmen photovoltaic power station of State Power Investment Jiangxi Company, since April 7 started construction, the construction scale is 7MWp, there are six 1.
    166MWp solar module arrays, the use of 265Wp solar photovoltaic modules, fixed installation mode, through the first phase of the photovoltaic project 35kV collector line into the line interval on the Internet, after the project is put into operation, the average annual utilization hours are about 891.
    25 hours, the design annual average power generation is 6.
    2976 million kWh
    .
    The grid-connected power generation of the project has added a new stroke
    to the company's energy development.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.