    The scientific construction of Shengli Dongxin operation area realizes the improvement of operation quality and efficiency

    • Last Update: 2021-08-28
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Sinopec News Network News This year, the Dongxin operation area of ​​the Shengli Oilfield Downhole Operation Center has been scientifically optimized in three aspects: construction personnel, operation dispatch and equipment relocation, to reduce the time loss of urban operations that cannot be carried out at noon and night
    .


    From January to July, a total of 812 wells were delivered, and the occupation period decreased by 0.


    The operation area has established an internal human resource allocation mechanism in response to the shortage of front-line personnel and the imbalance of personnel in various operation teams.
    Through internal circulation, the construction team personnel who take measures such as stoppages and well inspections are temporarily transferred to operations with shortage of personnel and full workload.
    Work in teams, optimize human resources, improve production efficiency, and ensure efficient operation of production in the work area
    .


    Since the beginning of this year, 283 people have been transferred within the operation area, 76 well-times were inspected by logistic personnel, 197 wells have been cross-powered in the operation area, and 483 people have been provided technical support by the agency personnel


    The work area can flexibly adjust the delivery time according to the limited construction time
    .


    For work wells that are prohibited from construction at night, the delivery time is changed to 6:30 for the morning shift and 18:30 for the night shift.


    The operation area is divided into regions according to the region.
    Each region is responsible for loading and unloading trucks by one crane.
    According to the daily relocation workload, one crane is used for maneuvering support.
    As a whole, the operation mode of crane regional hoisting and overall truck rotation is formed, saving the slow speed of cranes.
    Relying on time, shorten the relocation construction time, and the average relocation construction time for each well is shortened by 1 hour
    .


    At the same time, the departure time of special vehicles has been advanced so that the relocation vehicles can reach the upper workover site before the road is restricted and prohibited.


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.