    On October 17, the parameters of the fifth single-unit capacity million-kilowatt hydrogenerator set runner on the left bank of Baihetan Hydropower Station met the high-quality requirements put forward by the Three Gorges Group, and successfully passed the acceptance, becoming the first runner to pass the acceptance under the condition of "zero counterweight"
    .

    The turbine-generator set runner has a maximum diameter of 8.
    62 meters, a height of 3.
    92 meters, and a weight of 346.
    5 tons, consisting of
    an upper crown, a lower ring and 15 blades of 10.
    5 tons.

    It is reported that the acceptance standard of the high-quality runner proposed by Three Gorges Group is that the unbalanced moment is less than 74Kg·m, and if the unbalanced moment measured in the static balance test is greater than this value, it is necessary to weld the counterweight in the runner
    .

    The unbalanced torque measured in the static balance test of the accepted runner is only 28.
    83Kg·m, which can reach the standard of high-quality runner without additional counterweight, and realize the first "zero counterweight"
    manufactured on site at the Baihetan runner site of Dongfang Motor.

    It is reported that the runner factory itself has formulated an internal acceptance standard of 50Kg·m, which is far lower than the value of 74Kg·m quality acceptance index
    .
    After the fifth runner passes the acceptance, it will be temporarily stored outside the runner processing plant and transported to the underground plant on the left bank of Baihetan Hydropower Station for hoisting
    .


    On October 17, the parameters of the fifth single-unit capacity million-kilowatt hydrogenerator set runner on the left bank of Baihetan Hydropower Station met the high-quality requirements put forward by the Three Gorges Group, and successfully passed the acceptance, becoming the first runner to pass the acceptance under the condition of "zero counterweight"
    .

    Hydropower station

    The turbine-generator set runner has a maximum diameter of 8.
    62 meters, a height of 3.
    92 meters, and a weight of 346.
    5 tons, consisting of
    an upper crown, a lower ring and 15 blades of 10.
    5 tons.

    It is reported that the acceptance standard of the high-quality runner proposed by Three Gorges Group is that the unbalanced moment is less than 74Kg·m, and if the unbalanced moment measured in the static balance test is greater than this value, it is necessary to weld the counterweight in the runner
    .

    The unbalanced torque measured in the static balance test of the accepted runner is only 28.
    83Kg·m, which can reach the standard of high-quality runner without additional counterweight, and realize the first "zero counterweight"
    manufactured on site at the Baihetan runner site of Dongfang Motor.

    It is reported that the runner factory itself has formulated an internal acceptance standard of 50Kg·m, which is far lower than the value of 74Kg·m quality acceptance index
    .
    After the fifth runner passes the acceptance, it will be temporarily stored outside the runner processing plant and transported to the underground plant on the left bank of Baihetan Hydropower Station for hoisting
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.