    In the past few days, the side walls of the radiation section of the No.
    3, No.
    5 and No.
    7 cracking furnaces of the 800,000-ton/year ethylene unit of the Gulei Refinery and Chemical Integration Project undertaken by the Tenth Construction Company of Refining and Chemical Engineering have been hoisted into place on a temporary basis, marking the The overall modular construction of the cracking furnace of the unit is in full swing


    .


    It is understood that the ethylene plant of the Gulei refining and chemical integration project has a total of 8 cracking furnaces, which are designed by Sinopec Engineering Construction Corporation (SEI) and are the leading equipment of the ethylene plant


    .


    In order to complete the cracking furnace construction task on schedule, Shijian Gulei Refining and Chemical Engineering Project Department, together with the owner, the general contractor and other units, is determined to innovate and plan accurately, boldly put forward the concept of "exchange time with space" in the design stage, and formulated "one site, The strategy of "two construction sites" is to separate the 8 cracking furnaces and carry out dislocation and simultaneous construction on the site and the modular construction site


    .


    In order to reduce the impact of the epidemic on the construction of the cracking furnace, the project department strengthened the communication and coordination with the owner and the general contractor, and opened up three key lines of returning to work, transportation of construction materials and equipment, and preparation of epidemic prevention materials.
    The overall modular construction is fully rolled out


    .


    "Although the deep modular construction of cracking furnace is the first attempt for us, Shijian Company has rich practical experience in the modular construction of large-scale equipment


    .


    At present, the Tenth Construction Gulei Refining and Chemical Engineering Project Department takes the "hundred days of tackling difficulties and creating benefits" as an opportunity to make great efforts in "management innovation and work efficiency improvement" to accelerate the overall modular construction of the cracking furnace of Gulei Refining and Chemical ethylene unit process to ensure the safe, high-quality and efficient progress of the entire project construction


    .


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.