Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Recently, the Hainan Refinery and Chemical 1 million tons/year ethylene project built by the Fifth Construction Company of Refinery and Chemical Engineering Group has 2.
6 million tons/year continuous reforming unit, 100,000 tons/year MTBE/butene-1 unit, 160,000 tons/year The butadiene extraction unit is handed over to a high standard
.
So far, the 6 sets of main units of the Hainan Refinery and Chemical Ethylene Project undertaken by Wujian Company have all been handed over to high standards
.
Since the start of construction, the project department has formulated construction plans, innovated management methods, strengthened information management, and extensively carried out party building and co-construction and labor competitions around the key path of the project to ensure the efficient operation of the project
.
In the process, in view of the large amount of steel structure installation and process pipeline welding, the project department adopted modular operation to improve construction efficiency and reduce the risk of high-altitude operations; automatic welding was used for process pipeline welding, which improved welding efficiency
.
Aiming at the characteristics of "high, large, dense, and concentrated" installations, adhere to the key monitoring of key operations, analyze and decompose unsafe factors, and implement various safety measures in detail to ensure safe, stable and accident-free construction operations
.
In terms of quality management, the project department ensures quality control through measures such as "visualization" of quality disclosure, "model guide" and "two-dimensional code" information management
.
At the same time, during the construction of the installation, the project department gave full play to the role of the grass-roots party organization as a fighting fortress and the vanguard and exemplary role of party members, and established a "party member commando team" and a "party member demonstration post".
Create a "labor competition", and party members and cadres take the lead in "comparing progress, safety, quality, and on-site management, creating a civilized construction site", and promoting project construction in an orderly manner
.
In the next stage, the ethylene project department of Wujian Hainan Refinery and Chemical Co.
, Ltd.
will organize the completion of the construction and the operation and maintenance work to ensure the successful commissioning of the device
.