Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Sinopec News Network reported on July 14, the last trestle bridge of the Zhenhai Base Coal Coke Storage and Transportation Project undertaken by the Nanjing Engineering Fifth Engineering Branch of Refining and Chemical Engineering Group was safely and smoothly in place, and the main structure of the coal coke storage and transportation project was fully integrated
.
The project's trestle is 120 meters long and has a total weight of more than 600 tons
.
In order to ensure the safety of hoisting, the project department conducted a lot of data analysis and calculation before construction, formulated a safe and feasible prefabrication work plan, and completed the prefabrication of the columns and trestle on schedule
.
The project department successfully completed the prefabrication of more than 600 tons of trestle steel structure and 12 large-scale hoisting in 37 days
.
In order to ensure the progress of the project, the 12 hoisting operations were carried out at night, and the project department conducted a targeted risk assessment.
Before hoisting, the construction personnel were provided with detailed safety technical clarifications, and all hoisting tasks were completed safely and smoothly
(Liu Jinjin and Li Shu)