Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Quanzhou Guoheng project propane propylene separation tower "dress and hat" mobilization meeting
Quanzhou Guoheng project propane propylene separation tower "dress and hat" mobilization meetingRecently, the Quanzhou Guoheng Project Department of Sinochem Sixth Construction South China Branch invited the owner of Guoheng, the general contractor of Jingding, and the supervisor Gao Zhi to participate in the mobilization meeting of "wearing clothes and hats" for the propylene-propane separation tower
.
At the mobilization meeting, the participating leaders proposed to resolutely complete the task of "rolling up their sleeves and working hard for 30 days, safety and zero accidents, quality and quantity and construction period"
.
The project department said that it will continue to carry forward the spirit of Sinochem Sixth Construction's "dare to fight, dare to work hard, not afraid of hardships and fatigue, and be able to win battles"
.
It is reported that the first phase of the Guoheng project will build 660,000 tons/year propane dehydrogenation (PDH) and 450,000 tons/year high-performance polypropylene (PP) units
.
The total investment is 6.
3 billion, 1.
2 billion has been invested from January to March 2022, and 4.
1 billion is planned for the whole year
.
The hoisting work of large-scale equipment of Ningbo Formosa Plastics Project has come to a successful conclusion
The hoisting work of large-scale equipment of Ningbo Formosa Plastics Project has come to a successful conclusionOn May 11, the last three large heat exchangers in the ISBL process area of the Ningbo Formosa PDH project, which was built by the Ningbo Formosa Plastics Project Department directly under Sinochem Sixth Construction, were successfully hoisted into place, marking the successful conclusion of the project's large-scale equipment hoisting work
.
The project is located in Formosa Plastics Industrial Park, Xiapu Town, Beilun District, Ningbo City, Zhejiang Province, covering an area of about 26.
5 hectares.
After the project is completed and put into operation, it will adopt the international leading technology to improve the propylene production capacity, which is of positive significance for improving the local petrochemical industry chain
.
The project was completed by Sinochem Sixth Construction from construction application to commissioning
.
Aiming at the limitations of the on-site operation site, the project department compiled a detailed hoisting plan through the preliminary on-site measurement and computer lofting simulation, and selected a 700-ton crawler crane with a counterweight to prevent overhanging.
The three heat exchangers were hoisted sequentially from north to south, and the final safe and smooth The completion of the hoisting indicates that the project will fully enter the stage of pipeline installation
.