    The installation speed of the first unit of the Lidi hydropower station broke records

    • Last Update: 2022-11-26
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    A few days ago, from the Lidi project of the 14th Bureau of Hydropower, the first unit of the Lidi Hydropower Station took 48 days from the rotor lifting in place on August 12 to the completion of the water filling test on September 30, creating the fastest speed of the current unit installation and refreshing the installation record
    of large-scale hydro turbine units in the hydropower industry.

    Located in Badi Township, Weixi County, Diqing Prefecture, Yunnan Province, Lidi Hydropower Station is the third level power station in the cascade development plan of the upper reaches of the Lancang River, with a dam site control basin area of 86,400 square kilometers and a total reservoir capacity of 072.
    5 million cubic meters
    .
    The hydropower station is a riverbed power station, with three single-unit capacity 140 MW axial flow rotary paddle units, which is currently the second largest axial flow rotary pulp unit with a single capacity in China, with a rotor diameter of 11.
    19 meters, which is also the second largest rotor diameter axial rotary pulp unit power station
    in China.

    The successful completion of the water filling test of Unit 1 laid a solid foundation
    for the successful commissioning of the first unit of the power station.

    A few days ago, from the Lidi project of the 14th Bureau of Hydropower, the first unit of the Lidi Hydropower Station took 48 days from the rotor lifting in place on August 12 to the completion of the water filling test on September 30, creating the fastest speed of the current unit installation and refreshing the installation record
    of large-scale hydro turbine units in the hydropower industry.

    A few days ago, from the Lidi project of the 14th Bureau of Hydropower, the first unit of the Lidi Hydropower Station took 48 days from the rotor lifting in place on August 12 to the completion of the water filling test on September 30, creating the fastest speed of the current unit installation and refreshing the installation record
    of large-scale hydro turbine units in the hydropower industry.
    Hydropower station.

    Located in Badi Township, Weixi County, Diqing Prefecture, Yunnan Province, Lidi Hydropower Station is the third level power station in the cascade development plan of the upper reaches of the Lancang River, with a dam site control basin area of 86,400 square kilometers and a total reservoir capacity of 072.
    5 million cubic meters
    .
    The hydropower station is a riverbed power station, with three single-unit capacity 140 MW axial flow rotary paddle units, which is currently the second largest axial flow rotary pulp unit with a single capacity in China, with a rotor diameter of 11.
    19 meters, which is also the second largest rotor diameter axial rotary pulp unit power station
    in China.

    Located in Badi Township, Weixi County, Diqing Prefecture, Yunnan Province, Lidi Hydropower Station is the third level power station in the cascade development plan of the upper reaches of the Lancang River, with a dam site control basin area of 86,400 square kilometers and a total reservoir capacity of 072.
    5 million cubic meters
    .
    The hydropower station is a riverbed power station, with three single-unit capacity 140 MW axial flow rotary paddle units, which is currently the second largest axial flow rotary pulp unit with a single capacity in China, with a rotor diameter of 11.
    19 meters, which is also the second largest rotor diameter axial rotary pulp unit power station
    in China.

    The successful completion of the water filling test of Unit 1 laid a solid foundation
    for the successful commissioning of the first unit of the power station.

    The successful completion of the water filling test of Unit 1 laid a solid foundation
    for the successful commissioning of the first unit of the power station.
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.