    Sinopec News Network News On August 7, the Hainan Ethylene Project Department of Ningbo Engineering held a "100-day labor competition for great leaders" summary and commendation meeting and "continuous tackling, six to six innovations" labor competition mobilization meeting
    .

    During the 100-day labor competition period, the Hainan Project Department of Ningbo Engineering focused on perfect design, final procurement, capping of the main structure of the main buildings such as 4 substations and power center main buildings, ground pipe construction, power station boiler equipment installation, The installation of water purification module equipment and the installation of water tanks and oil tanks are the main lines to fully mobilize various resources, increase human and material resources, and adopt unconventional measures to tap the resources of the five teams in the potential project to support each other and concentrate their efforts.
    Fight the war of annihilation
    .


    With the hard work of all parties, the goals of each node have been achieved, creating favorable conditions for the large-scale implementation of the next stage of installation and construction


    Next, the project will shift from civil construction to the key stage of installation.
    The Hainan Project Department of Ningbo Engineering will start the August-October project with the theme of "continuously tackling tough problems, six-to-six innovations, and concerted efforts to promote the construction of Hainan Refining and Chemical Ethylene Project".
    Labor competition activities, bite the two 110KV substations to reach the power receiving conditions on October 30; 35KV water treatment substations to reach the power receiving conditions on November 15; 35KV chemical zone substations to reach the power receiving conditions on November 30 The water purification plant will be delivered on September 30; the desalinated water and condensed water recovery device will be delivered on October 30; the pyrolysis gasoline and naphtha tank will be delivered on January 25 next year; the fire station will be delivered at the end of January next year; power The first boiler of the center will produce steam on January 25 next year, and the goal of full-scale delivery on April 30 next year will not be shaken.
    When the Charge is sounded, we will work harder to ensure safety, quality, progress, and stability.
    , Set off a new climax of installation and construction, and ensure the smooth realization of the goals of the various nodes of the labor competition
    .


    (Yang Li)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.