    The first unit of the Guoduo hydropower station will generate electricity as planned

    • Last Update: 2022-11-20
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    It is understood that at the end of this month, the first unit of the Guoduo Hydropower Station will generate electricity as planned, with an annual power generation capacity of 300 million kilowatt-hours in full operation, which can send a steady stream of power energy
    to the land of the three rivers.

    Duan Chuan, general manager of Huaneng Guoduo Hydropower Co.
    , Ltd.
    , said that as of the end of November, the Guoduo Hydropower Station has completed a cumulative investment of 2.
    722 billion yuan, accounting for 71%
    of the total investment.
    The total construction period of the Guoduo Hydropower Station project is planned to be 63 months, and the river will be intercepted by the end of 2012, the main project will start construction in January 2013, the water will be stored under the diversion tunnel in November 2015, and the project will be completed
    in June 2016.

    The total investment of Guoduo Hydropower Station is 3.
    833 billion yuan, with a total installed capacity of 165,000 kilowatts and an annual power generation capacity of 831.
    9 million kilowatt-hours
    .
    The hydropower station is located in Chaiwei Township, Karo District, Changdu, 59 kilometers away from the county seat of Qamdo, and is the second rung of the Zhaqu plan, and the project is a third-class project, and the project scale is medium-sized
    .
    The storage capacity below the normal water storage level is 79.
    59 million square meters, the regulated storage capacity is 17.
    46 million square meters, with weekly regulation performance, and the installed capacity of the power station is 160 MW
    .

     

    It is understood that at the end of this month, the first unit of the Guoduo Hydropower Station will generate electricity as planned, with an annual power generation capacity of 300 million kilowatt-hours in full operation, which can send a steady stream of power energy
    to the land of the three rivers.

    Guoduo Hydropower Station

    Duan Chuan, general manager of Huaneng Guoduo Hydropower Co.
    , Ltd.
    , said that as of the end of November, the Guoduo Hydropower Station has completed a cumulative investment of 2.
    722 billion yuan, accounting for 71%
    of the total investment.
    The total construction period of the Guoduo Hydropower Station project is planned to be 63 months, and the river will be intercepted by the end of 2012, the main project will start construction in January 2013, the water will be stored under the diversion tunnel in November 2015, and the project will be completed
    in June 2016.

    The total investment of Guoduo Hydropower Station is 3.
    833 billion yuan, with a total installed capacity of 165,000 kilowatts and an annual power generation capacity of 831.
    9 million kilowatt-hours
    .
    The hydropower station is located in Chaiwei Township, Karo District, Changdu, 59 kilometers away from the county seat of Qamdo, and is the second rung of the Zhaqu plan, and the project is a third-class project, and the project scale is medium-sized
    .
    The storage capacity below the normal water storage level is 79.
    59 million square meters, the regulated storage capacity is 17.
    46 million square meters, with weekly regulation performance, and the installed capacity of the power station is 160 MW
    .

     

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.