Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
This Spring Festival, at the project site of the second phase of the nuclear power plant of GFC Guangxi Fangchenggang nuclear power in China's "Hualong No.
1" demonstration project, nuclear power builders have stuck to their jobs, and the on-site construction has been carried out
normally and continuously.
On February 13, the third layer dome plate and the first ring hanging corbel of Fangchenggang Nuclear Power Unit 3 were installed in place, laying the foundation
for the dome lifting of Fangchenggang Unit 3.
It is reported that the steel lining ring hanging corbel installation and the 3rd layer plate hoisting of Fangchenggang Unit 3 are in the critical path
of dome lifting.
Among them, the use of corbels is a prerequisite for the installation of
ring cranes.
The smooth placement of the first ring hanging corbel of Fangchenggang Unit 3 indicates that the construction technology of Hualong No.
1 corbel has matured
.
On February 12, the pouring of the 15th layer (non-reserved area) of the inner shell of Unit 3 of Fangchenggang was completed, and the lifting of the fourth layer of the steel-lined cylinder of Unit 4 was completed
.
In order to ensure the smooth construction of the Hualong No.
1 demonstration project, the Fangchenggang Project Department of CGN Engineering Corporation planned in advance, carefully organized, actively coped with the impact of the windy weather in the Fangchenggang area in winter, reasonably organized the on-site labor resources before and after the Spring Festival, and steadily promoted the construction of the critical path of the dome lifting of the Fangchenggang Unit 3 and the civil construction of the nuclear island
.
This Spring Festival, at the project site of the second phase of the nuclear power plant of GFC Guangxi Fangchenggang nuclear power in China's "Hualong No.
1" demonstration project, nuclear power builders have stuck to their jobs, and the on-site construction has been carried out
normally and continuously.
On February 13, the third layer dome plate and the first ring hanging corbel of Fangchenggang Nuclear Power Unit 3 were installed in place, laying the foundation
for the dome lifting of Fangchenggang Unit 3.
It is reported that the steel lining ring hanging corbel installation and the 3rd layer plate hoisting of Fangchenggang Unit 3 are in the critical path
of dome lifting.
Among them, the use of corbels is a prerequisite for the installation of
ring cranes.
The smooth placement of the first ring hanging corbel of Fangchenggang Unit 3 indicates that the construction technology of Hualong No.
1 corbel has matured
.
On February 12, the pouring of the 15th layer (non-reserved area) of the inner shell of Unit 3 of Fangchenggang was completed, and the lifting of the fourth layer of the steel-lined cylinder of Unit 4 was completed
.
In order to ensure the smooth construction of the Hualong No.
1 demonstration project, the Fangchenggang Project Department of CGN Engineering Corporation planned in advance, carefully organized, actively coped with the impact of the windy weather in the Fangchenggang area in winter, reasonably organized the on-site labor resources before and after the Spring Festival, and steadily promoted the construction of the critical path of the dome lifting of the Fangchenggang Unit 3 and the civil construction of the nuclear island
.