Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On the afternoon of November 9th, Qu Chunlin, general manager of the President Office of Wanda Group, led a team to the Witt Production Division of Tianhong Company to inspect and accept
the pilot project of butane to acetone.
Li Zenggang, assistant to the chairman of the board of Wanda Group and executive president of Wanda Petrochemical Group, Jia Tongchun, executive director of Wanda Petrochemical Research Institute, and Jia Huaixing, general manager of Witt Production Division of Tianhong Company, attended the acceptance
.
The acceptance team inspected the operation of the device on site and carried out detailed inspections
of key equipment and the central control room.
Afterwards, the acceptance team went to the conference room on the first floor of Witt Production Division to listen to the project introduction in detail and carefully check
the various materials of the installation.
Through on-site inspection, listening to reports and reviewing materials, the acceptance team highly recognized the butane to acetone pilot project and was full of hope for the future of the project, and the acceptance team unanimously agreed that the butane to acetone pilot project passed the acceptance
.
It is reported that the butane to acetone pilot project uses cheap isobutane as raw material to produce acetone, and the process route is the first in China
.
The project began construction in September 2021 and was completed in September 2022, and the device has reached the pilot test conditions
.
In the next step, Wanda Petrochemical Group will actively carry out various work under the correct leadership of the board of directors of the group company, coordinate the preparation for the start and commissioning of the project, ensure that the project is put into production as soon as possible, and contribute to