Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Sinopec News Network reported on July 16, the steel structure of the ethylene glycol plant supervisor gallery of Hainan Refining & Chemical's 1 million tons/year ethylene project undertaken by the Fourth Branch of Nanjing Engineering Company ushered in the first modular hoisting, and the steel structure installation was officially opened.
The work program screen successfully realized the control nodes required by the labor competition
.
The main gallery of the ethylene glycol plant has a total of 47 axes with a total length of 292 meters.
The total weight of the upper four-story steel structure is about 1480 tons, which accounts for 30% of the total steel structure of the plant
.
In order to ensure the construction period, the project department planned the overall plan, strictly in accordance with the labor competition nodes formulated by the owner from the civil construction stage, and completed the civil construction within the node time with quality and quantity, laying a solid foundation for steel structure installation and ensuring that the steel structure is on time Hoisting
Due to the recent rain in Hainan, in order to improve the level of civilized construction on site, the project department immediately carried out road construction and ground hardening work after the completion of the pipe gallery foundation construction, speeding up soilless construction, and ensuring construction safety, quality and progress
.
They maintain close contact with the manufacturing plant and continue to track the delivery of steel structure materials.
The first hoisting of the steel structure of the main gallery was completed, which created conditions for subsequent process piping and equipment installation, marking the transition of the glycol device from the civil construction stage to the installation stage, which opened the prelude to on-site installation
.
All the staff of the project department will continue to work hard and overcome difficulties to ensure that the project progresses as planned and contribute to the early completion and delivery of the project
(Gao Wenlu Li Shu)