Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Sinopec News Network reported on August 25, with the smooth start-up of two natural gas compressors, the first domestic water-bearing trap-type gas storage design project designed by the Petroleum Engineering Design Company-"Yong'an Oilfield Yong21 Block Underground Storage The “gas storage construction project” was successfully put into operation
.
After four months of intensive design and operation and three months of high-quality on-site service, the petroleum engineering design company’s wall chart operations, efficient linkage, and high-quality work to fully promote the construction of important people’s livelihood projects, provide safe gas supply for Shengli Oilfield and surrounding areas Important guarantee
The company established an independent design team composed of 4 senior experts from petroleum engineering construction companies, 12 company experts, 31 majors, and 85 designers
.
Company leaders listen to special reports on the project every day
In accordance with the concept of maximizing the value of the whole life cycle, the design team strictly follows the "five modernizations" concept to design, spatially and intensively arrange the process equipment and pipelines, the standardized design coverage rate reaches 80%, the skid-mounted rate reaches 95%, and the station yard is three-dimensional The design rate has reached 100%, the digital design and delivery rate has reached 100%, the overall design efficiency has increased by 20%, and the design quality has increased by 9%; in the case of tight station space, the combined plant installations in the station have greatly reduced the area occupied and compared with conventional storage.
Compared with the gas storage project, it saves 12.
2% of land
.
The design team submitted the construction drawings in batches 5 days in advance and was highly praised by the owner
(Yin Qian, Sun Zhifeng and Yu Pengpeng)