Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
The construction of the ethylene plant of the Guangdong Petrochemical Refining and Chemical Integration Project ushered in a milestone node at 10:30 on November 30.
The ethylene plant of the Guangdong Petrochemical Project has a total of 6 double-chamber liquid furnaces and 2 double-chamber gas furnaces, each with a scale of 200,000 tons per year, of which the liquid furnace is the largest single-chamber scale in China
The construction of cracking furnace overcomes difficulties such as narrow operation site, long construction period and cross operation.
In the next step, according to the mid-term delivery plan on March 30, 2022, with the national demonstration project as the goal and strict organization as the guarantee, the builders will make every effort to speed up the construction progress, improve the construction efficiency, and ensure the high-quality mid-term delivery of the ethylene plant of the Guangdong Petrochemical Project.