Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
us">
.
.
.
.
.
.
.
.
On May 24, the No.
3 and No.
7 cracking furnaces of the 800,000-ton/year steam cracking unit of the Gulei Refinery and Chemical Integration Project undertaken by the Tenth Construction Company of the Refining and Chemical Engineering Group were successfully ignited
.
On May 24, the No.
3 and No.
7 cracking furnaces of the 800,000-ton/year steam cracking unit of the Gulei Refinery and Chemical Integration Project undertaken by the Tenth Construction Company of the Refining and Chemical Engineering Group were successfully ignited
.
On May 24, the No.
3 and No.
7 cracking furnaces of the 800,000-ton/year steam cracking unit of the Gulei Refinery and Chemical Integration Project undertaken by the Tenth Construction Company of the Refining and Chemical Engineering Group were successfully ignited
.
On May 24, the No.
3 and No.
7 cracking furnaces of the 800,000-ton/year steam cracking unit of the Gulei Refinery and Chemical Integration Project undertaken by the Tenth Construction Company of the Refining and Chemical Engineering Group were successfully ignited
.
On May 24, the No.
3 and No.
7 cracking furnaces of the 800,000-ton/year steam cracking unit of the Gulei Refinery and Chemical Integration Project undertaken by the Tenth Construction Company of the Refining and Chemical Engineering Group were successfully ignited
.
On May 24, the No.
3 and No.
7 cracking furnaces of the 800,000-ton/year steam cracking unit of the Gulei Refinery and Chemical Integration Project undertaken by the Tenth Construction Company of the Refining and Chemical Engineering Group were successfully ignited
.
It is understood that there are a total of 8 cracking furnaces in the ethylene plant.
Up to now, a total of 7,000 tons of cracking furnace steel structures have been installed, the process pipelines are more than 400,000 inches in diameter, 112 sets of equipment have been installed, 400,000 meters of electrical instrumentation cables have been laid, 4,800 instruments have been installed, and instruments have been installed.
6,000 construction tasks such as loop joint schools
.
It is understood that there are a total of 8 cracking furnaces in the ethylene plant.
Up to now, a total of 7,000 tons of cracking furnace steel structures have been installed, the process pipelines are more than 400,000 inches in diameter, 112 sets of equipment have been installed, 400,000 meters of electrical instrumentation cables have been laid, 4,800 instruments have been installed, and instruments have been installed.
6,000 construction tasks such as loop joint schools
.
It is understood that there are a total of 8 cracking furnaces in the ethylene plant.
Up to now, a total of 7,000 tons of cracking furnace steel structures have been installed, the process pipelines are more than 400,000 inches in diameter, 112 sets of equipment have been installed, 400,000 meters of electrical instrumentation cables have been laid, 4,800 instruments have been installed, and instruments have been installed.
6,000 construction tasks such as loop joint schools
.
It is understood that there are a total of 8 cracking furnaces in the ethylene plant.
Up to now, a total of 7,000 tons of cracking furnace steel structures have been installed, the process pipelines are more than 400,000 inches in diameter, 112 sets of equipment have been installed, 400,000 meters of electrical instrumentation cables have been laid, 4,800 instruments have been installed, and instruments have been installed.
6,000 construction tasks such as loop joint schools
.
It is understood that there are a total of 8 cracking furnaces in the ethylene plant.
Up to now, a total of 7,000 tons of cracking furnace steel structures have been installed, the process pipelines are more than 400,000 inches in diameter, 112 sets of equipment have been installed, 400,000 meters of electrical instrumentation cables have been laid, 4,800 instruments have been installed, and instruments have been installed.
6,000 construction tasks such as loop joint schools
.
It is understood that there are a total of 8 cracking furnaces in the ethylene plant.
Up to now, a total of 7,000 tons of cracking furnace steel structures have been installed, the process pipelines are more than 400,000 inches in diameter, 112 sets of equipment have been installed, 400,000 meters of electrical instrumentation cables have been laid, 4,800 instruments have been installed, and instruments have been installed.
6,000 construction tasks such as loop joint schools
.
In order to ensure the successful ignition of the No.
3 and No.
7 cracking furnaces, the project department made overall planning and careful organization, strictly implemented safety, quality, and progress management measures, concentrated superior resources, and ensured the efficient operation of the project
.
All construction workers gave up rest and vacations, and stayed on their posts during the festival.
All professional construction personnel worked together with the production workshop to work overtime to purge the air tightness.
In strict accordance with the cracking furnace oven condition confirmation table, they completed each construction task item by item and ignited the furnace.
Be well prepared
.
During the construction process of the project, the Shijian Gulei Refining and Chemical Engineering Project Department took the labor competition of "anchoring the target, focusing on the decisive battle for 60 days" as the action goal, overcoming various external factors such as the epidemic, late arrival of materials and drawings, and "innovation".
Management and improving work efficiency” as the work orientation, optimized and improved the construction plans of various specialties many times, vigorously promoted modular construction, reduced cross-operation of various specialties, avoided construction operation risks, and effectively improved construction work efficiency
.
With the joint efforts of all employees involved in the construction, the cracking furnace of the ethylene plant has officially entered the trial operation stage
.
It has laid a solid foundation for the safe, high-quality and long-term stable operation of the device
.
In order to ensure the successful ignition of the No.
3 and No.
7 cracking furnaces, the project department made overall planning and careful organization, strictly implemented safety, quality, and progress management measures, concentrated superior resources, and ensured the efficient operation of the project
.
All construction workers gave up rest and vacations, and stayed on their posts during the festival.
All professional construction personnel worked together with the production workshop to work overtime to purge the air tightness.
In strict accordance with the cracking furnace oven condition confirmation table, they completed each construction task item by item and ignited the furnace.
Be well prepared
.
In order to ensure the successful ignition of the No.
3 and No.
7 cracking furnaces, the project department made overall planning and careful organization, strictly implemented safety, quality, and progress management measures, concentrated superior resources, and ensured the efficient operation of the project
.
All construction workers gave up rest and vacations, and stayed on their posts during the festival.
All professional construction personnel worked together with the production workshop to work overtime to purge the air tightness.
In strict accordance with the cracking furnace oven condition confirmation table, they completed each construction task item by item and ignited the furnace.
Be well prepared
.
In order to ensure the successful ignition of the No.
3 and No.
7 cracking furnaces, the project department made overall planning and careful organization, strictly implemented safety, quality, and progress management measures, concentrated superior resources, and ensured the efficient operation of the project
.
All construction workers gave up rest and vacations, and stayed on their posts during the festival.
All professional construction personnel worked together with the production workshop to work overtime to purge the air tightness.
In strict accordance with the cracking furnace oven condition confirmation table, they completed each construction task item by item and ignited the furnace.
Be well prepared
.
In order to ensure the successful ignition of the No.
3 and No.
7 cracking furnaces, the project department made overall planning and careful organization, strictly implemented safety, quality, and progress management measures, concentrated superior resources, and ensured the efficient operation of the project
.
All construction workers gave up rest and vacations, and stayed on their posts during the festival.
All professional construction personnel worked together with the production workshop to work overtime to purge the air tightness.
In strict accordance with the cracking furnace oven condition confirmation table, they completed each construction task item by item and ignited the furnace.
Be well prepared
.
In order to ensure the successful ignition of the No.
3 and No.
7 cracking furnaces, the project department made overall planning and careful organization, strictly implemented safety, quality, and progress management measures, concentrated superior resources, and ensured the efficient operation of the project
.
All construction workers gave up rest and vacations, and stayed on their posts during the festival.
All professional construction personnel worked together with the production workshop to work overtime to purge the air tightness.
In strict accordance with the cracking furnace oven condition confirmation table, they completed each construction task item by item and ignited the furnace.
Be well prepared
.
During the construction process of the project, the Shijian Gulei Refining and Chemical Engineering Project Department took the labor competition of "anchoring the target, focusing on the decisive battle for 60 days" as the action goal, overcoming various external factors such as the epidemic, late arrival of materials and drawings, and "innovation".
Management and improving work efficiency” as the work orientation, optimized and improved the construction plans of various specialties many times, vigorously promoted modular construction, reduced cross-operation of various specialties, avoided construction operation risks, and effectively improved construction work efficiency
.
With the joint efforts of all employees involved in the construction, the cracking furnace of the ethylene plant has officially entered the trial operation stage
.
It has laid a solid foundation for the safe, high-quality and long-term stable operation of the device
.
During the construction process of the project, the Shijian Gulei Refining and Chemical Engineering Project Department took the labor competition of "anchoring the target, focusing on the decisive battle for 60 days" as the action goal, overcoming various external factors such as the epidemic, late arrival of materials and drawings, and "innovation".
Management and improving work efficiency” as the work orientation, optimized and improved the construction plans of various specialties many times, vigorously promoted modular construction, reduced cross-operation of various specialties, avoided construction operation risks, and effectively improved construction work efficiency
.
With the joint efforts of all employees involved in the construction, the cracking furnace of the ethylene plant has officially entered the trial operation stage
.
It has laid a solid foundation for the safe, high-quality and long-term stable operation of the device
.
During the construction process of the project, the Shijian Gulei Refining and Chemical Engineering Project Department took the labor competition of "anchoring the target, focusing on the decisive battle for 60 days" as the action goal, overcoming various external factors such as the epidemic, late arrival of materials and drawings, and "innovation".
Management and improving work efficiency” as the work orientation, optimized and improved the construction plans of various specialties many times, vigorously promoted modular construction, reduced cross-operation of various specialties, avoided construction operation risks, and effectively improved construction work efficiency
.
With the joint efforts of all employees involved in the construction, the cracking furnace of the ethylene plant has officially entered the trial operation stage
.
It has laid a solid foundation for the safe, high-quality and long-term stable operation of the device
.
During the construction process of the project, the Shijian Gulei Refining and Chemical Engineering Project Department took the labor competition of "anchoring the target, focusing on the decisive battle for 60 days" as the action goal, overcoming various external factors such as the epidemic, late arrival of materials and drawings, and "innovation".
Management and improving work efficiency” as the work orientation, optimized and improved the construction plans of various specialties many times, vigorously promoted modular construction, reduced cross-operation of various specialties, avoided construction operation risks, and effectively improved construction work efficiency
.
With the joint efforts of all employees involved in the construction, the cracking furnace of the ethylene plant has officially entered the trial operation stage
.
It has laid a solid foundation for the safe, high-quality and long-term stable operation of the device
.
During the construction process of the project, the Shijian Gulei Refining and Chemical Engineering Project Department took the labor competition of "anchoring the target, focusing on the decisive battle for 60 days" as the action goal, overcoming various external factors such as the epidemic, late arrival of materials and drawings, and "innovation".
Management and improving work efficiency” as the work orientation, optimized and improved the construction plans of various specialties many times, vigorously promoted modular construction, reduced cross-operation of various specialties, avoided construction operation risks, and effectively improved construction work efficiency
.
With the joint efforts of all employees involved in the construction, the cracking furnace of the ethylene plant has officially entered the trial operation stage
.
It has laid a solid foundation for the safe, high-quality and long-term stable operation of the device
.
During the construction process of the project, the Shijian Gulei Refining and Chemical Engineering Project Department took the labor competition of "anchoring the target, focusing on the decisive battle for 60 days" as the action goal, overcoming various external factors such as the epidemic, late arrival of materials and drawings, and "innovation".
Management and improving work efficiency” as the work orientation, optimized and improved the construction plans of various specialties many times, vigorously promoted modular construction, reduced cross-operation of various specialties, avoided construction operation risks, and effectively improved construction work efficiency
.
With the joint efforts of all employees involved in the construction, the cracking furnace of the ethylene plant has officially entered the trial operation stage
.
It has laid a solid foundation for the safe, high-quality and long-term stable operation of the device
.