    The civil construction of the 100,000-ton/year BDO project of the fifth phase of Sino-Thai-Meike Chemical Industry started

    • Last Update: 2022-11-04
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On July 15, the "first shovel" of the 100,000-ton/year BDO project of the fifth phase of Sino-Thaimeike broke ground.
    The excavators and loaders roared one after another, and the construction scene was in full swing

    .

    It is understood that the preliminary procedures for the project were handled smoothly, and the long-term equipment has been ordered
    .
    At present, the preliminary design is being prepared, the "three links and one leveling" on site have been basically completed, and the excavators and loaders are ready to be in place

    .
    The project builds 4 sets of process units of 25,000 tons/year of calcium carbide method acetylene, 100,000 tons/year of 1,4-butanediol, 240,000 tons/year of formaldehyde, and 13,000Nm3/h of hydrogen production; supporting thermoelectric devices, tar furnaces, Circulating water, desalinated water station & reuse water, air pressure nitrogen station, production water pump station, whole plant torch, power transformation and distribution, cabinet room, whole plant ground pipe/external pipe, etc.
    The project covers an area of ​​333 mu, with a total investment of 2.
    693 billion yuan , the average annual operating income is 2,452.
    59 million yuan, the average annual profit and tax total is 463.
    84 million yuan, and 266 jobs are created

    .

    Groundbreaking ceremony

    The road ahead has suddenly become clear, and it is determined that we must step up
    .
    Zhongtaimeike Chemical will focus on the overall control of the trinity (safety, quality, progress), focus on process execution and contract performance, lock in key time nodes, push the progress backwards with nodes, and urge the construction unit to make full use of machinery, manpower, Inverted schedule, wall chart combat

    .
    And take this as an opportunity to overcome difficulties, work tenaciously, forge ahead with determination, and become an enterprise that "can do things and achieve things"

    .

    After the project is put into operation, it will rejuvenate the oil and natural gas sector, activate new kinetic energy, further release Xinjiang Zhongtai Group's BDO superior production capacity, and become an important part of the strategic layout of Zhongtai Group's industrial chain extension, supplementary chain, strong chain, and chain expansion.
    In the first link, it will continue to occupy the maximization of the scale of domestic BDO products and the commanding heights of technology

    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.