    The 1.2 million tons/year catalytic cracking unit of Beihai Refining & Chemical Co., Ltd. successfully started up at one time

    • Last Update: 2021-08-13
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On the afternoon of August 7, the 1.
    2 million tons/year catalytic cracking unit of the Beihai Refining and Chemical Restructuring and Reconstruction Project undertaken by the Fourth Construction Company of Petrochemical Corporation was successfully injected with one fuel injection, the whole process was opened up, and the unit was successfully started up, marking the full start of the structural adjustment and reconstruction project.
    Put into production
    .

    The Beihai Refining and Chemical Restructuring and Restructuring Project is a key project for Beihai Refining and Chemical Company to achieve quality improvement and efficiency upgrade and strive to build a world-class refining and chemical enterprise
    .


    Petrochemical Fourth Construction Company undertook the construction of a new 1.


    In the pre-construction preparation stage, due to the objective impact of the new crown epidemic at home and abroad, there was a serious shortage of personnel and various procedures were seriously lagging behind, which brought unprecedented difficulties and challenges to the project construction organization
    .


    In order to ensure that the project does not cause a cluster of epidemic outbreaks, the project department actively cooperates with the owner to conduct nucleic acid testing for all employees, track each person’s journey and body temperature, conduct joint prevention and control, implement grid-based measures, weave a strong prevention and control network, and block Break the transmission chain, ensure that there are no personnel from medium and high-risk areas entering the site, and make every effort to ensure the construction of a "zero infection" project


    In terms of construction difficulty and progress, the construction of the catalytic converter has always been the top priority of the overall construction.
    The project started the prefabrication of the steel structure of the catalytic device in June, and the overall casting of the concrete frame of the catalytic converter was completed on September 5
    .


    On October 26, the V201/202 feedstock oil/refining tank was successfully installed


    In terms of construction difficulty and progress, the construction of the catalytic converter has always been the top priority of the overall construction.


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.