Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Since the end of December, the 300,000-ton/year high-end polypropylene project in Shandong Weifang, which was built by the Tenth Construction Company of Refining and Chemical Engineering, has been completed.
It is understood that the 300,000-ton/year high-end polypropylene project in Weifang is a key project for the conversion of new and old kinetic energy in Shandong, and is faced with many unfavorable factors such as tight construction schedules and complex geological conditions
Facing the construction period of only one year for the high-end polypropylene project in Weifang, the project department took "management innovation and work efficiency improvement" as its work orientation, and successively implemented steel structure and equipment modularization, pipeline prefabrication factory, and quality management informatization 12 The construction technology innovation and work efficiency improvement measures have not only improved the quality and efficiency of the project construction, but also effectively reduced the frequency of various risks and hidden dangers such as high-altitude operation and lifting and hoisting, and further strengthened the project construction safety management and control line of defense
As of December 25, the construction workers of the project department have completed 94% of the total process pipeline installation, and all the construction tasks such as the single-machine commissioning of the motor have been completed, laying the groundwork for the high-end PP project in Weifang to achieve the goal of high-standard delivery in late January 2022.