Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
During the "May 1st" period, nearly 3,000 employees of the tenth construction company of the refining and chemical engineering company adhered to the Yushan Island in Zhoushan, Zhejiang, and pushed forward the construction of the second phase of the Zhejiang Petrochemical project at full speed to ensure that the project achieved the high-standard delivery goal on schedule.
In the construction of the project, the Shijian Company undertook the construction of two sets of 3 million tons/year slurry bed residual oil hydrogenation, 400,000 tons/year LDPE and other 8 sets of equipment construction tasks.
In view of the unfavorable situation of the coming rainy season, the project department took precautions, sorted out the construction plans of each device in advance, organized various professional construction leaders to optimize and perfect the construction organization of the remaining projects, and ensure that the safety, quality, and progress of the construction in the later stage of the project are always in place.
At present, under the hard work of the staff participating in the construction of the project department, 80% of the total construction of two 3 million tons/year slurry bed residual oil hydrogenation units has been completed, 300,000 tons/year LDPE+EVA and 400,000 tons/year Over 60% of the annual LDPE device construction tasks were completed, laying a solid foundation for the timely realization of the project’s high-standard delivery goals.
(Tian Yuanwu)