Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Since the beginning of October, the Tenth Construction Company of Refining and Chemical Engineering has taken various measures to promote the soilless construction of Yangzi Petrochemical's refining adjustment project, creating favorable conditions for high-quality operation of the project
.
It is understood that Nanjing, where the Yangzi Petrochemical Refining Adjustment Project is located, has a subtropical humid monsoon climate.
There is a long rainy season in spring and summer.
Long-term rainfall will affect the underground pipeline network, civil construction, large equipment hoisting, steel structure, and pipelines.
In-depth cross-construction of multiple disciplines such as welding has caused many difficulties such as frequent safety risks, decreased construction quality, and slow construction progress
.
Faced with the total ground hardening capacity of approximately 63,000 square meters in the main equipment of the Yangzi Petrochemical’s refining structure adjustment project, such as catalytic cracking, gas fractionation, and catalytic gasoline adsorption desulfurization, the project department continued to improve and optimize the two major professional construction organization plans of civil engineering and underground pipe network.
The overall construction goal of the refining structure adjustment project formulated by Yangzi Petrochemical will continue to accelerate the speed of ground hardening and soilless construction, and create a good construction environment for equipment, steel structures, process pipelines, electrical instruments and other professions
.
According to calculations conducted by the project department, if the Yangzi Petrochemical refining structure adjustment project adopts ground hardening and soilless construction in advance, it is expected that the frequency of safety risks caused by lifting and temporary power use during the construction of the project will be reduced by about 60%, and the construction efficiency will be reduced.
Increased by about 2 times
.
After the ground hardening and soilless construction is implemented, the hidden dangers of construction operations will be significantly reduced, and the construction work environment of participating employees will be greatly improved, laying a solid foundation for achieving the goal of safe, environmentally friendly and green construction sites
.