    Ten Construction Company continues to build a strong line of construction safety control and defense in the rainy season

    • Last Update: 2021-06-22
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Since the beginning of June, the key construction projects of Gulei Refining & Chemical, Zhejiang Petrochemical Phase II, Fujian United Petrochemical, Shandong Weifang High-end Polypropylene and other key construction projects undertaken by the Tenth Construction Company of Refining & Chemical Engineering have entered the rainy season construction stage
    .

    The company strictly implemented the general manager's No.
    2 order, took the "five inspections and five stricts" special safety action as an opportunity, combined with the safety production month activities in June, paid close attention to the process safety management of key construction projects, and continued to strengthen the safety control and defense line of construction operations during the rainy season
    .

    "There is a cable in this distribution box that is damaged.
    It must be replaced in time.
    Now that the rain is frequent and the humidity is high, it is necessary to prevent temporary power hazards in time
    .


    " On June 13, the second phase of the Zhejiang Petrochemical Project was undertaken by the Ten Construction Company.


    The project department benchmarked safety management standards, rectified the weak links of safety management at the construction operation level in an all-round and three-dimensional manner, and effectively created a safe and stable project construction environment for participating employees
    .

    At the 800,000 tons/year ethylene plant site of the Gulei Refining and Chemical Integration Project undertaken by Shijian Company, the project department took precautions and deployed sandbags, raincoats and other typhoon and flood prevention equipment in advance to comprehensively prevent areas prone to water accumulation
    .


    Since the beginning of the spring, the Gulei area in Zhangzhou, Fujian has received sparse rainfall, but the project department strictly controls the construction safety management requirements during the rainy season, and strengthens the office roofs, exhibition boards, processing plants and other areas that are vulnerable to typhoon rain to ensure the entire rainy season.


    In early June, rains in Gulei began to increase, and thunderstorms were frequent.


      "Underground pipe network construction must prevent hidden dangers of landslides due to heavy rainfall, and excavation of trenches must strictly implement the operation ticket system.


      According to the current project construction priorities, the project department conducts centralized rectification of risks and hidden dangers in key areas and key links such as civil concrete pouring, steel tying, trench excavation, and underground pipe network installation to ensure the safe and efficient progress of various construction nodes in the rainy season


      At present, under the strong management and control of the safety management departments at all levels of the Ten Construction Company, the construction safety management of each key construction project in the rainy season is under control


      ​(Tian Yuanwu)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.