Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On the morning of August 28th, with the hoisting of the steam turbine of the last pyrolysis gas compressor unit of the 800,000-ton/year ethylene project of the Zhongke Refining and Chemical Integration Project, the lifting and installation work of the 10 compressor units of the project was faster than planned on August 3 It was completed 3 days ahead of schedule, which is another great achievement achieved by the engineering construction company's Zhongke project meticulously organizing, commanding and coordinating, the tenth construction company working hard against time, and the shipping company closely cooperating with the large-scale hoisti.
The ten compressor units in the ethylene project are sorted by area and model as follows: C-201 large-scale pyrolysis gas compressor unit with a total weight of 331 tons in the compression area; C-301R/X methane tail gas expander/recompressor unit in the cold area, C-302 low-pressure methane Compressor unit, C-501 large-scale propylene refrigeration compressor unit, C-601 large-scale ethylene refrigeration compressor unit; C-665A ethylene bubble point gas compressor for low temperature tank farm, C-665B ethylene bubble point gas compressor, C-666A propylene refrigeration compressor machine, C-666B propylene refrigeration compressor; C-760 second-stage circulating hydrogen compressor unit in gasoline hydrogenation zo.
The ten compressor units were packaged separately and shipped to the Zhongke site, including dozens of high-pressure cylinders, medium-pressure cylinders, low-pressure cylinders, steam turbines, electric motors, foundation bases, oil stations, and water recuperato.
In order to ensure that these equipments arrive at the Zhongke site on schedule, the general contractor of the engineering construction company on the one hand intensified efforts to urge the production plant to deliver on time, and on the other hand increased the foundation of the civil subcontractor's compressor un.
Safety and quality are the eternal them.
Compressor is not only high-tech equipment, but also the "heart" of a device syst.
The large-scale hoisting engineer of the Zhongke project of the shipping company has prepared a hoisting plan in advance, and according to the plan, the large-scale crane station is filled with rubble and gravel to be filled and flattened to pass the acceptance; In the process of hoisting, the commander's orders are accurate, the driver is skilled in operating smoothly and at a constant speed, and each hoisting is completed safe.
In this way, under the concerted efforts of all the employees of the participating units, the first ten compressors were installed from July 13, and they were all completed on August 2 "Strengthen management, build image, promote degree, and fight for 90 days" labor competition activity node - the goal of installing the ethylene compressor unit on August 31 is 3 days ahead of schedu.