    Tarim ethane cracking to ethylene achieved a stage victory!

    • Last Update: 2022-08-22
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On April 26, Room A of the radiant section of No.
    1 furnace was in place 

    On April 27th, Room B of the radiant section of No.
    1 furnace was in place

    On April 28, Room A of the radiant section of No.
    2 furnace was in place 

    So far, the installation of the radiant section of the cracking furnace of the Tarim Ethane to Ethylene Project Department has been successfully completed


    .


    The 119 class of riveting pipes interprets the speed of six constructions

    The 119 class of riveting pipes interprets the speed of six constructions

    Team 119 of the project department is responsible for the prefabrication of Room A in the radiation section of the No.
    1 furnace of the ethylene cracking furnace.
    According to the requirements of the node, the team leader Wang Jianfeng has to redeploy the division of labor of the team members for the day before going to work every day


    .


    The prefabrication of the furnace implements the concept of "five modernizations", and promotes the prefabrication process with high efficiency through the flow-type operation of fixed personnel and designated points


    .


    Everyone in Class 119 "refused" to work overtime.
    The brothers worked together and kept their energy.
    Look at this top-notch work efficiency, where is the need for overtime? 

    Comprehensive management and control upgrade safety and quality peers

    Comprehensive management and control upgrade safety and quality peers

     "Inspection, implementation, and rectification" are the recent key words of the Tarim Ethane-to-Ethylene Project Department.
    In order to efficiently complete the cracking furnace construction task on the premise of ensuring safety and quality, the project department continuously optimizes the management mode and improves the on-site construction.
    Control strength


    .


    Since the resumption of work this year, in terms of safety management, the project department has organized a total of 18 special trainings, 36 on-site trainings, and carried out 3 emergency drills, 2 monthly safety inspections, and 2 pre-holiday inspections


    .


    In terms of technical quality, the project department strictly implements the construction plan review system, strengthens the review of drawings, and at the same time makes full technical disclosures on specific construction methods, procedures and quality specifications before on-site construction


    .


    It is imperative to focus on quality and efficiency improvement projects

    It is imperative to focus on quality and efficiency improvement projects

    With room A of the radiant section of the No.
    2 furnace in place, all 10 sets of radiant section modules of the cracking furnace of the ethylene unit of the Tarim Ethane-to-Ethylene Project have been installed, and the project construction has achieved a phased victory


    .


    Facing the severe situation of the global spread of the epidemic and the decline of international oil prices, the Tarim ethane-to-ethylene project, as a key project for PetroChina's refining and chemical transformation and upgrading and a key project for PetroChina to create a world-class demonstration enterprise, is imperative to improve quality and efficiency


    .


    The project department will continue to promote the utilization of the CIMS platform, improve the material identification management, and promote the construction process and improve construction efficiency by strengthening information management
    .
    At the same time, the project department will adhere to innovative management thinking, optimize the management mode, and promote the overall improvement of the project construction quality through lean management

    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.