    Summary of domestic styrene plant maintenance in 2020

    • Last Update: 2022-08-16
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Before the festival, the editor compiled a summary list of styrene plant maintenan.


    As a result, the related industries are faced with many challenges and difficulti.


    Company Name

    Capacity

    Maintenance time

    Qingdao Bay

    50

    1 month scheduled maintenance in March 2020

    Tianjin Dagu

    50

    From March 16th to May 9th, 2020, overhaul for 45 da.


    Oriental Petrochemical

    12

    45 days for maintenance in March-April 2020

    Ningbo Keyuan

    20

    From mid-April to mid-June, 2020, it will be shut down for maintenance, and the olefin project supporting technical renovation will start .


    BASF Yangtze

    12

    April 6, 2020 - May 17, 42 days of maintenance

    Qilu Petrochemical

    20

    Maintenance from May 4th to May 30th, 2020

    Sinopec

    5

    May 12-July 19, 2020

    Maoming Petrochemical

    10

    60 days of maintenance in early May 2020

    Yanshan Petrochemical

    8

    46 days of maintenance from July 19, 2020 to September 2

    Jiujiang Petrochemical

    8

    August 25, 2020 - October 18, 2020 overhaul for 55 days

    Shanghai Secco

    65

    35 days for maintenance from October 8th to November 11th, 2020

    Baling Petrochemical

    12

    From October 14, 2020 to November 27, 2020, the parking lot will be stopped for 45 days, and the maintenance will be synchronized with the refine.


    Guangzhou Petrochemical

    8

    From November 2, 2020 to November 16, 15 days of maintenance

    Jiangsu Listel

    twenty one

    There is an overhaul plan for styrene in 2020, uncertain, and the possibility of the second half of the year is high

    Company Name

    Capacity

    Maintenance time

    Qingdao Bay

    50

    1 month scheduled maintenance in March 2020

    Tianjin Dagu

    50

    From March 16th to May 9th, 2020, overhaul for 45 da.


    Oriental Petrochemical

    12

    45 days for maintenance in March-April 2020

    Ningbo Keyuan

    20

    From mid-April to mid-June, 2020, it will be shut down for maintenance, and the olefin project supporting technical renovation will start .


    BASF Yangtze

    12

    April 6, 2020 - May 17, 42 days of maintenance

    Qilu Petrochemical

    20

    Maintenance from May 4th to May 30th, 2020

    Sinopec

    5

    May 12-July 19, 2020

    Maoming Petrochemical

    10

    60 days of maintenance in early May 2020

    Yanshan Petrochemical

    8

    46 days of maintenance from July 19, 2020 to September 2

    Jiujiang Petrochemical

    8

    August 25, 2020 - October 18, 2020 overhaul for 55 days

    Shanghai Secco

    65

    35 days for maintenance from October 8th to November 11th, 2020

    Baling Petrochemical

    12

    From October 14, 2020 to November 27, 2020, the parking lot will be stopped for 45 days, and the maintenance will be synchronized with the refine.


    Guangzhou Petrochemical

    8

    From November 2, 2020 to November 16, 15 days of maintenance

    Jiangsu Listel

    twenty one

    There is an overhaul plan for styrene in 2020, uncertain, and the possibility of the second half of the year is high

    Company Name

    Capacity

    Maintenance time

    Company Name

    Company Name

    company name company name company name

    Capacity

    Capacity

    capacity capacity

    Maintenance time

    Maintenance time

    overhaul time overhaul time

    Qingdao Bay

    50

    1 month scheduled maintenance in March 2020

    Qingdao Bay

    Qingdao Bay

    Qingdao Bay

    50

    50

    50

    1 month scheduled maintenance in March 2020

    1 month scheduled maintenance in March 2020

    1 month scheduled maintenance in March 2020

    Tianjin Dagu

    50

    From March 16th to May 9th, 2020, overhaul for 45 da.


    Tianjin Dagu

    Tianjin Dagu

    Tianjin Dagu

    50

    50

    50

    From March 16th to May 9th, 2020, overhaul for 45 da.


    From March 16th to May 9th, 2020, overhaul for 45 da.


    From March 16th to May 9th, 2020, overhaul for 45 da.


    12

    45 days for maintenance in March-April 2020

    Oriental Petrochemical

    Oriental Petrochemical

    Oriental Petrochemical

    12

    12

    12

    45 days for maintenance in March-April 2020

    45 days for maintenance in March-April 2020

    45 days for maintenance in March-April 2020

    Ningbo Keyuan

    20

    From mid-April to mid-June, 2020, it will be shut down for maintenance, and the olefin project supporting technical renovation will start .


    Ningbo Keyuan

    Ningbo Keyuan

    Ningbo Keyuan

    20

    20

    20

    From mid-April to mid-June, 2020, it will be shut down for maintenance, and the olefin project supporting technical renovation will start .


    From mid-April to mid-June, 2020, it will be shut down for maintenance, and the olefin project supporting technical renovation will start .


    From mid-April to mid-June, 2020, it will be shut down for maintenance, and the olefin project supporting technical renovation will start .


    12

    April 6, 2020 - May 17, 42 days of maintenance

    BASF Yangtze

    BASF Yangtze

    BASF Yangtze

    12

    12

    12

    April 6, 2020 - May 17, 42 days of maintenance

    April 6, 2020 - May 17, 42 days of maintenance

    April 6, 2020 - May 17, 42 days of maintenance

    Qilu Petrochemical

    20

    Maintenance from May 4th to May 30th, 2020

    Qilu Petrochemical

    Qilu Petrochemical

    Qilu Petrochemical

    20

    20

    20

    Maintenance from May 4th to May 30th, 2020

    Maintenance from May 4th to May 30th, 2020

    Maintenance from May 4th to May 30th, 2020

    Sinopec

    5

    May 12-July 19, 2020

    Sinopec

    Sinopec

    Sinopec

    5

    5

    5

    May 12-July 19, 2020

    May 12-July 19, 2020

    May 12-July 19, 2020

    Maoming Petrochemical

    10

    60 days of maintenance in early May 2020

    Maoming Petrochemical

    Maoming Petrochemical

    Maoming Petrochemical

    10

    10

    10

    60 days of maintenance in early May 2020

    60 days of maintenance in early May 2020

    60 days of maintenance in early May 2020

    Yanshan Petrochemical

    8

    46 days of maintenance from July 19, 2020 to September 2

    Yanshan Petrochemical

    Yanshan Petrochemical

    Yanshan Petrochemical

    8

    8

    8

    46 days of maintenance from July 19, 2020 to September 2

    46 days of maintenance from July 19, 2020 to September 2

    46 days of maintenance from July 19, 2020 to September 2

    Jiujiang Petrochemical

    8

    August 25, 2020 - October 18, 2020 overhaul for 55 days

    Jiujiang Petrochemical

    Jiujiang Petrochemical

    Jiujiang Petrochemical

    8

    8

    8

    August 25, 2020 - October 18, 2020 overhaul for 55 days

    August 25, 2020 - October 18, 2020 overhaul for 55 days

    August 25, 2020 - October 18, 2020 overhaul for 55 days

    Shanghai Secco

    65

    35 days for maintenance from October 8th to November 11th, 2020

    Shanghai Secco

    Shanghai Secco

    Shanghai Secco

    65

    65

    65

    35 days for maintenance from October 8th to November 11th, 2020

    35 days for maintenance from October 8th to November 11th, 2020

    35 days for maintenance from October 8th to November 11th, 2020

    Baling Petrochemical

    12

    From October 14, 2020 to November 27, 2020, the parking lot will be stopped for 45 days, and the maintenance will be synchronized with the refine.

    Baling Petrochemical

    Baling Petrochemical

    Baling Petrochemical

    12

    12

    12

    From October 14, 2020 to November 27, 2020, the parking lot will be stopped for 45 days, and the maintenance will be synchronized with the refine.

    From October 14, 2020 to November 27, 2020, the parking lot will be stopped for 45 days, and the maintenance will be synchronized with the refine.

    From October 14, 2020 to November 27, 2020, the parking lot will be stopped for 45 days, and the maintenance will be synchronized with the refine.

    Guangzhou Petrochemical

    8

    From November 2, 2020 to November 16, 15 days of maintenance

    Guangzhou Petrochemical

    Guangzhou Petrochemical

    Guangzhou Petrochemical

    8

    8

    8

    From November 2, 2020 to November 16, 15 days of maintenance

    From November 2, 2020 to November 16, 15 days of maintenance

    From November 2, 2020 to November 16, 15 days of maintenance

    Jiangsu Listel

    twenty one

    There is an overhaul plan for styrene in 2020, uncertain, and the possibility of the second half of the year is high

    Jiangsu Listel

    Jiangsu Listel

    Jiangsu Listel

    twenty one

    twenty one

    twenty one

    There is an overhaul plan for styrene in 2020, uncertain, and the possibility of the second half of the year is high

    There is an overhaul plan for styrene in 2020, uncertain, and the possibility of the second half of the year is high

    There is an overhaul plan for styrene in 2020, uncertain, and the possibility of the second half of the year is high

    With the epidemic under control, domestic enterprises and factories have resumed work one after another recently , logistics and transportation have gradually resumed, and the procurement of raw materials by enterprises in various provinces will be improv.

    Market demand is expected to increase in Marc.

    However, the medium and long-term equipment maintenance variables still exist, and the above maintenance plan will continue to follow up and repor.

    With the epidemic under control, domestic enterprises and factories have resumed work one after another recently , logistics and transportation have gradually resumed, and the procurement of raw materials by enterprises in various provinces will be improv.

    Market demand is expected to increase in Marc.

    However, the medium and long-term equipment maintenance variables still exist, and the above maintenance plan will continue to follow up and repor.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.