Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
"The last base tower has been accepted!" On November 26, State Grid Putian Power Supply Company dispatched a total of 120 people for 5 days to successfully complete the acceptance task of the 140 base tower of the 220 kV Dunzhuang Line from Daitou Confluence Station to Shangzhuang, laying a solid foundation
for the smooth connection of offshore wind power on Nanri Island.
It is reported that the line is a 220 kV overhead line project for the Nanri Island offshore wind power project in Xiuyu District, Putian City
.
In order to do a good job in the acceptance of the wind power line, Putian Power Supply Company carefully deployed and carefully arranged the relevant work
on the morning of the 22nd.
During the acceptance process, the company strictly follows the specifications of the acceptance items, follows the safety regulations to climb the tower for inspection, and communicates and docks with the line engineering and technical personnel in time to ensure that the defects are rectified in place
.
Since another 28 base towers are located on Nanri Island, the company's staff traveled to the island by ferry to carry out acceptance work
.
In order to help the new energy grid integration work, all the personnel involved in the acceptance of the company's transmission and transportation inspection room took the initiative to give up weekend rest time and work overtime to ensure the progress of
this acceptance work.
As of the 26th, with the joint efforts of all employees, the line acceptance task has been completed
.
Nanri Island has superior terrain and abundant wind power resources, and the 220 kV Dunzhuang line from Daitou Confluence Station to Shangzhuang provides a transmission channel
for new energy.
After the line is put into operation, it will add a clean and renewable energy "artery" to the Putian power grid and inject "green power"
into it.
"The last base tower has been accepted!" On November 26, State Grid Putian Power Supply Company dispatched a total of 120 people for 5 days to successfully complete the acceptance task of the 140 base tower of the 220 kV Dunzhuang Line from Daitou Confluence Station to Shangzhuang, laying a solid foundation
for the smooth connection of offshore wind power on Nanri Island.
It is reported that the line is a 220 kV overhead line project for the Nanri Island offshore wind power project in Xiuyu District, Putian City
.
In order to do a good job in the acceptance of the wind power line, Putian Power Supply Company carefully deployed and carefully arranged the relevant work
on the morning of the 22nd.
During the acceptance process, the company strictly follows the specifications of the acceptance items, follows the safety regulations to climb the tower for inspection, and communicates and docks with the line engineering and technical personnel in time to ensure that the defects are rectified in place
.
Since another 28 base towers are located on Nanri Island, the company's staff traveled to the island by ferry to carry out acceptance work
.
In order to help the new energy grid integration work, all the personnel involved in the acceptance of the company's transmission and transportation inspection room took the initiative to give up weekend rest time and work overtime to ensure the progress of
this acceptance work.
As of the 26th, with the joint efforts of all employees, the line acceptance task has been completed
.
Nanri Island has superior terrain and abundant wind power resources, and the 220 kV Dunzhuang line from Daitou Confluence Station to Shangzhuang provides a transmission channel
for new energy.
After the line is put into operation, it will add a clean and renewable energy "artery" to the Putian power grid and inject "green power"
into it.