Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On November 28, the 1.
The project delivery ceremony was held in the on-site meeting room of the Zhenhai base.
The project delivery ceremony was held in the on-site meeting room of the Zhenhai base.
The Zhenhai Refining and Chemical Engineering Project started on May 7, 2020.
The basic design of Zhenhai ethylene plant was approved for 21 months.
At present, the pressure test of the pipeline of the device has been completed, the cracking furnace has been baked, the no-load commissioning of the three units has been completed, the single test of the machine pump has been completed except for the material that needs to be introduced, the purging and reset of the pipeline has been basically completed, and the heat preservation has been completed 91.
Sinopec Zhenhai Base Project shoulders the great responsibility of "building Sinopec's flagship benchmarking enterprise and guiding the future development of Sinopec".
With the strong support of , supervisors and all parties involved in the construction, the tenth construction company has improved its position, the leadership is "in command", systematically supervises, and "integrates the power of the company" to advance collaboratively, firmly control the key control points, focus on safety, quality assurance, Grab the progress and ensure the project is completed on time.
This is the crystallization of the sweat and wisdom of Shijian people and all participating units
.
Finally, he demanded that the project department continue to be closely organized, strict requirements, accurate control, and steady progress
.
Conscientiously implement various safety, quality and progress guarantee measures in the production preparation, closely cooperate with the workshop to do various production preparations, and "anchor 12.
30" to ensure that the device is successfully started and fed once, and the product is qualified once
.