Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On December 3, the first batch of 4 sections of 100 tons of propylene, which was the raw material for the ethylene plant, was unloaded at the plant, marking that the Sino-Korea Petrochemical Area has entered the stage of preparation for the overhaul of the Sino-Korea Petrochemical Area
.
During the original start-up period and during the major overhaul in 2016, Sino-Korea Petrochemical used propylene for the ethylene plant to be produced from refining and stored in the tank before the overhaul as the starting material.
During this overhaul, the propylene storage tank had to be constructed and shut down.
The propylene in the rear storage tank needs to be completely emptied, the refining storage tank will store 1,200 tons, and the rest of the gap should be extracted from propylene before the start of construction
.
During the original start-up period and during the major overhaul in 2016, Sino-Korea Petrochemical used propylene for the ethylene plant to be produced from refining and stored in the tank before the overhaul as the starting material.
In order to reduce the investment cost, the company transformed the original propylene factory facilities in the highway loading and unloading station through technical transformation and delivered it for use in late November
.
Before the unloading facility was put into use, the chemical production management department organized relevant professionals to confirm the unloading conditions
.
On December 3, the first car of propylene entered the plant, and under the coordination and organization of relevant departments, the relevant procedures were completed to confirm the start of unloading, and the unloading was completed successfully at noon
.