    Sijian Shenguan, Zhongke Refinery and Chemical High-density Polyethylene, etc. to accelerate the process of commissioning

    • Last Update: 2022-08-21
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On January 5, 2020, it was learned from the Zhongke Refinery and Chemical Project under construction that the sixth division of the Zhongke Refinery and Chemical Project, which is managed by the management team of the Fourth Construction Engineering Project Management Company, participated in the PMC management.
    Since the completion of the four major projects of ethylene and 350,000 tons/year polypropylene plant on November 30, 2019, the three inspections and four determinations, pipeline pressure test and installation and commissioning of electrical instruments have been accelerated to ensure the smooth progress of the commissioning work


    .


    According to reports, the sixth division of Zhongke Refining and Chemical Project, which is managed by the management team of the Fourth Construction Engineering Project Management Company, is mainly responsible for the management of Zhongke Refining and Chemical's 350,000 tons/year HDPE high-density polyethylene, 350,000 tons/year polypropylene, 200,000 tons/year polypropylene, 2.
    4 million tons/year S-Zorb catalytic gasoline adsorption desulfurization unit, polymer three-dimensional warehouse and other 5 main project management contents, all of which are contracted by the engineering construction company EPC.
    The 350,000-ton/year HDPE high-density polyethylene plant of Kelian Chemical was constructed by Sinopec No.
    4 Company, and the other four main projects were constructed by Sinopec No.
    5 Company


    .


    In order to complete the commissioning work of 5 main projects including 350,000 tons/year HDPE high-density polyethylene of Zhongke Refinery on schedule, the sixth division of the Zhongke Refinery project starts from each process of construction, and first pays close attention to the finishing work of the construction.
    Focus on three investigations and four determinations for rectification, organize weekly matchmaking meetings, and urge all construction majors to accelerate rectification and elimination; secondly, pay close attention to the management of pipeline pressure testing packages, and urge construction units to submit pressure testing package data for approval in a timely manner to ensure pipeline testing.
    The pressure work was carried out smoothly, relying on the pipeline pressure test to speed up the completion of the process pipeline; finally, carefully organize the electrical instrument installation work, on the one hand, urge the electrical construction unit to speed up the installation of electrical equipment, speed up cable laying and installation and wiring, to gain time for single-machine trial operation On the other hand, urge the instrument construction unit to actively carry out the single school of instrument equipment, organize manpower to fully seize the instrument cable laying and instrument wiring between cabinets, and create conditions for the instrument joint school


    .


    Thanks to the joint efforts of the sixth division of the Zhongke Refinery and Chemical Project and all participating units, since the project started in June 2018, a total of about 2,700 pile foundations have been constructed, about 110,000 cubic meters of concrete have been poured, and about 1.
    3 million cubic meters of steel structures have been installed.
    10,000 tons, installed nearly 900 sets of static and dynamic equipment, about 400,000 inches of process pipeline welding, about 150 kilometers of process pipelines, nearly 1,000 sets of electrical equipment, nearly 6,000 sets of instrumentation equipment, and nearly 2,000 kilometers of electrical and instrument cables.
    There are nearly 1,000 pressure test packages for process pipelines


    .


    Up to now, the sixth division of Zhongke Refining and Chemical Project is actively urging all participating units to make work arrangements before and after the Spring Festival, to ensure the continuity of construction during the Spring Festival, and to gain time for the Zhongke Refining and Chemical Project to start the project on schedule


    .


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.