    Significant progress has been made in the Hainan refining and chemical project of Shanghai Engineering

    • Last Update: 2022-08-29
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Recently, the light components removal and EO refining frame (31 frame) of Hainan Refinery and Chemical's 800,000 t/a EG unit was successfully capped, followed by the EO reaction frame (11 frame), which also successfully capped the concrete structure


    .


    11 The total height of the frame is 36.
    5 meters, with a three-story concrete structure and two-story steel structure, with a total of six spans and an area of ​​1,300 square meters


    .


    11 The total height of the frame is 36.


    As the steel concrete structure framework of the two main processes of Hainan EG installation, the project team has organized and planned with the awareness of "starting is a decisive battle, and starting is a sprint" after its establishment.


    The first batch of 2 large towers of the EG plant has successfully arrived at the ethylene-owned terminal of Hainan Refinery and Chemical before the National Day, and is ready to enter the site
    .


    After the successful topping of the 11 and 31 frame concrete structures, it took 20 days to dismantle the scaffolding
    .
    The large-scale equipment carried by the two frames will arrive at the site at the end of October and can be smoothly connected and installed in place, which has laid a solid foundation for the subsequent installation of steel structures and the full deployment of the installation of more than 100,000-inch diameter pipes of the two frames.
    foundation

    .
    The project team will maintain the spirit of "standing at the forefront and striving for the first", and continue to strive for the completion of the "June 89" work target set by the headquarters at the end of the year

    .
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.