Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Recently, Senvion confirmed the conversion
of a firm order for a 300 MW wind power contract with alfanar India.
The signing
of the order for the Bhuj project was announced in early December 2018.
The project scope includes a full EPC for 131 Senvion 2.
3M130 turbines that will be installed in the second quarter of 2020 as well as a complete operation and maintenance contract
.
The wind power project in the Indian state of Gujarat is part of the fifth round of bidding by Solar Energy Corporation of India, a company
in the Ministry of New and Renewable Energy of the Indian government.
In addition to this project, Senvion and alfanar have signed another order
for the 300 MW project in India.
In 2018, Senvion's orders in India totaled more than 1 GW, including 730 MW.
It is understood that the order was booked at the end of December 2018 and took effect
in cash in the first week of January 2019.
:/, please indicate the source for reprinting)
Recently, Senvion confirmed the conversion
of a firm order for a 300 MW wind power contract with alfanar India.
The signing
of the order for the Bhuj project was announced in early December 2018.
The project scope includes a full EPC for 131 Senvion 2.
3M130 turbines that will be installed in the second quarter of 2020 as well as a complete operation and maintenance contract
.
The wind power project in the Indian state of Gujarat is part of the fifth round of bidding by Solar Energy Corporation of India, a company
in the Ministry of New and Renewable Energy of the Indian government.
In addition to this project, Senvion and alfanar have signed another order
for the 300 MW project in India.
In 2018, Senvion's orders in India totaled more than 1 GW, including 730 MW.
It is understood that the order was booked at the end of December 2018 and took effect
in cash in the first week of January 2019.
:/, please indicate the source for reprinting)
/